No project in Melvindale City, but 6 nearby
Who decides here: the City Council of Melvindale City votes on zoning. The Wayne County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Solstice Data center, Enterprise Drive, Allen Park
Allen Park, Wayne County
🕒 June 4, 2026: Planning commission voted 7-2 to deny the site plan and asked the city to pause data cen…
Stopped or cancelledabout 6 miles awayWarehouse data center conversion, Southern Street, Inkster
Inkster, Wayne County
🕒 Oct 19, 2026: At a packed meeting, no city council member moved to approve the permit, so it was never…
Proposedabout 8 miles awayProposed data center on city land, Shoemaker Street, Detroit
Detroit, Wayne County
14.4 acres
🕒 March 2026: City council voted 6-2 to ask the mayor for a two-year pause on data center permits.
Reported in the news, not confirmed yet
Proposedabout 12 miles awayRaeden data center at former McLouth Steel site, Gibraltar
Gibraltar, Wayne County
🕒 Aug 2026: Raeden and landowner Cal Realty sued the city in federal court over the pause.
Being builtabout 14 miles awayGoogle data center (Project Cannoli), Van Buren Township
Van Buren Township, Wayne County
282 acres · for Google
🕒 Oct 30, 2026: Michigan Attorney General Dana Nessel asked state utility regulators (MPSC) to rehear th…
Approved, not built yetabout 14 miles awayMetrobloks data center, Southfield
Southfield, Oakland County
12 acres
🕒 Dec 15, 2025: City council voted 5-2 to approve the site plan.
Local votes and rules
🤝 Agreement with the company · Wayne County
The Wayne County Commission voted 13-0 to override County Executive Warren Evans's Sept. 25 veto of tax breaks for the Google data center in Van Buren Township.
What you can do
- Get told first.
We'll email you if anything changes in Melvindale City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Melvindale City: Wyandotte Municipal Serv Comm (run by the town) or DTE Electric Company (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Michigan.