๐Ÿ“ฃ Report Something
USA โ€บ Michigan โ€บ Oakland County โ€บ Southfield City
Approved, not built yet

Metrobloks data center, Southfield

Metrobloks plans a two-story, 100-megawatt data center on about 12 acres on Inkster Road. City council approved it 5-2 over residents' concerns about power use and electric rates. The company says it will use a closed-loop cooling system.

โœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: City council approved the site plan 5-2 in December 2025.

๐Ÿ•’ Latest update (Dec 15, 2025): City council voted 5-2 to approve the site plan.

What we know

  • ๐Ÿ“ WhereEast side of Inkster Road between 11 Mile Road and I-696, Southfield, Oakland County
  • ๐Ÿข CompanyMetrobloks
  • ๐ŸŒณ Size12 acres
  • โšก Power it needs100 megawatts (about as much as 80,000 homes)
  • โ„๏ธ Coolingclosed-loop cooling
  • ๐Ÿ’ต Cost$1.5 billion
  • ๐Ÿ‘ท Jobs promised35

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Dec 15, 2025
    City council voted 5-2 to approve the site plan.

Local votes and rules

โœ… Approved

Southfield City Council voted 5-2 to approve the site plan for Metrobloks' 100-megawatt data center on about 12 acres near Inkster Road, between 11 Mile Road and I-696.

Dec 15, 2025
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Southfield City Council greenlights divisive data center plan: 'Too many unknowns' ยท Planet Detroit ยท Dec 16, 2025
  2. How many AI data centers are planned in Michigan? We counted. ยท Gander Newsroom ยท March 2, 2026

See something wrong? Tell us and we'll fix it.