Solstice Data center, Enterprise Drive, Allen Park

Solstice Data proposed a 26-megawatt data center on Enterprise Drive near homes and a high school. After three delays, planners denied it, saying the plans were missing information and did not show noise would be controlled.

✔ ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: Planning commission denied the site plan 7-2 on June 4, 2026. The company could appeal.

🕒 Latest update (June 4, 2026): Planning commission voted 7-2 to deny the site plan and asked the city to pause data centers for six months.

What we know

  • 📍 WhereEnterprise Drive south of I-94, near homes and a high school, Allen Park, Wayne County
  • 🏢 CompanySolstice Data
  • ⚡ Power it needs26 megawatts (about as much as 20,800 homes)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • June 4, 2026
    Planning commission voted 7-2 to deny the site plan and asked the city to pause data centers for six months.
🛰️ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

📣 Report something

Where this comes from

  1. Allen Park planners reject proposed data center: 'We're gonna celebrate with one eye open' · Planet Detroit · June 5, 2026
  2. How many AI data centers are planned in Michigan? We counted. · Gander Newsroom · March 2, 2026

See something wrong? Tell us and we'll fix it.