Stopped or cancelled
Solstice Data center, Enterprise Drive, Allen Park
Solstice Data proposed a 26-megawatt data center on Enterprise Drive near homes and a high school. After three delays, planners denied it, saying the plans were missing information and did not show noise would be controlled.
Where things stand: Planning commission denied the site plan 7-2 on June 4, 2026. The company could appeal.
🕒 Latest update (June 4, 2026): Planning commission voted 7-2 to deny the site plan and asked the city to pause data centers for six months.
What we know
- 📍 WhereEnterprise Drive south of I-94, near homes and a high school, Allen Park, Wayne County
- 🏢 CompanySolstice Data
- ⚡ Power it needs26 megawatts (about as much as 20,800 homes)
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Did Solstice appeal to the Zoning Board of Appeals? 🙋 I'll find out
What happened so far
- June 4, 2026Planning commission voted 7-2 to deny the site plan and asked the city to pause data centers for six months.
🛰️ See it from above
An aerial photo of the area.
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.
Where this comes from
- Allen Park planners reject proposed data center: 'We're gonna celebrate with one eye open' · Planet Detroit · June 5, 2026
- How many AI data centers are planned in Michigan? We counted. · Gander Newsroom · March 2, 2026
See something wrong? Tell us and we'll fix it.