Proposed data center on city land, Shoemaker Street, Detroit

A company pitched a data center for a city-owned site on Shoemaker Street on Detroit's east side. Details are confidential. City council asked the mayor to pause data center permits for two years while the city writes rules.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Detroit City.

Where things stand: Proposed A data center pitch was among answers to a city request for proposals. City council asked the mayor for a two-year pause in March 2026.

❓ 2 open questions about it: see below.

Last checked Oct 10, 2026.

🕒 Latest update (March 2026): City council voted 6-2 to ask the mayor for a two-year pause on data center permits.

What we know

  • 📍 WhereCity-owned Shoemaker development site on the east side, near Coleman A. Young airport, Detroit, Wayne County
  • 🏢 Companyunknown
  • 🌳 Size14.4 acres

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Who proposed the data center and how big would it be? 🙋 I'll find out ·
  • Did the mayor adopt the two-year pause? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • March 2026
      City council voted 6-2 to ask the mayor for a two-year pause on data center permits.

    Local votes and rules

    ⏸️ Pause on new data centers

    A council member asked the council's lawyers to draft a zoning pause on permits for new large AI data centers until March 17, 2028. It has not been introduced. Most council members favor the planning commission's permanent data center rules instead, which they aim to approve by Dec. 31.

    Sept 29, 2026

    📌 Other

    Detroit City Council voted 6-2 to ask the mayor to stop new data center permits for two years while the city writes rules. The mayor's office said it would review the request. The city has no data center zoning rules yet.

    March 17, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Detroit council calls for 2-year data center freeze · Planet Detroit · March 18, 2026
    2. Data center moratorium for Detroit · BridgeDetroit · March 18, 2026
    3. Request for Proposals: Shoemaker Development Site, 11031 & 11081 Shoemaker St. · City of Detroit Housing & Revitalization Department (via DEGC) · Oct 27, 2025
    4. Data center proposed for 14.4 acres on Detroit's east side; city council seeks moratorium · WXYZ Detroit · March 2026

    See something wrong? Tell us and we'll fix it.