Send us a tip
Being builtBig (AI-size): 1,000 megawatts

Google data center (Project Cannoli), Van Buren Township

Also called: Project Cannoli

Google plans a 1-gigawatt data center on 282 acres in Van Buren Township near Detroit Metro Airport. DTE would serve it with new solar and batteries. Google must pay for at least 80% of its contracted power. Planet Detroit reported it could use 2 to 3.6 million gallons of water a day.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Township Board of Van Buren Charter Township.

Where things stand: Being built Construction has started: foundation pouring began the week of Oct. 26, 2026 after final site plan approval on Oct. 14.

  • Nov 16, 2026: Our records now list Google data center (Project Cannoli), Van Buren Township as being built Source
  • Oct 1, 2026: Wayne County: agreement adopted Source

❓ 2 open questions about it: see below.

📬 Get an email about this project

One email when something important changes. No account. Unsubscribe any time.

We use your email only for updates about Google data center (Project Cannoli), Van Buren Township. Privacy

Last checked Nov 16, 2026.

🕒 Latest update (Oct 30, 2026): Michigan Attorney General Dana Nessel asked state utility regulators (MPSC) to rehear their approval of DTE's power contracts for the Google data center (case U-22058). She wants yearly checks of costs and benefits so other DTE customers do not end up paying, or the contracts rejected.

What we know

  • 📍 WhereNorth of I-94, east of Haggerty Road and south/west of I-275, west of Detroit Metro Airport, Van Buren Township, Wayne County
  • 🏢 CompanyPanattoni Development
  • 👤 Built forGoogle
  • 🌳 Size282 acres
  • ⚡ Power it needs1,000 megawatts (about as much as 800,000 homes)
  • 🔌 Where the power comes fromDTE Energy, with up to 1,600 MW of new solar and 480 MW of batteries under the contract
  • 💧 WaterGreat Lakes Water Authority · 3,600,000 gallons a day
  • 💸 Tax breaksTax exemption worth over $125 million, approved by the Wayne County Commission.
  • 👷 Jobs promised51

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Did the township sign a development agreement with Google, and what does it say? 🙋 I'll find out ·
  • How will state regulators (MPSC) rule on the Attorney General's request to rehear the DTE-Google power contracts? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: news reports place the 282 acres between Haggerty Road on the west and I-94 and I-275 on the south and east. The pin is in the middle of that land.

    What happened so far

    • Feb 2026
      Township planning commission gave preliminary site plan approval.
    • March 18, 2026
      DTE filed the power contracts with state regulators as a full contested case.
    • Oct 2, 2026
      State utility regulators (MPSC) voted 3-0 to approve DTE's 20-year power contracts with Google, with conditions.
    • Oct 14, 2026
      Township planning commission voted 5-1 to approve the final site plan. Plans use 150 of the 282 acres for six buildings, parking, a substation and equipment yards.
    • Oct 26, 2026
      Foundation pouring for the buildings began this week, after tree clearing and site grading by developer Panattoni. The state (EGLE) had issued wetland, stream crossing and air permits.
    • Oct 30, 2026
      Michigan Attorney General Dana Nessel asked state utility regulators (MPSC) to rehear their approval of DTE's power contracts for the Google data center (case U-22058). She wants yearly checks of costs and benefits so other DTE customers do not end up paying, or the contracts rejected.

    Local votes and rules

    🤝 Agreement with the company

    The Wayne County Commission voted 13-0 to override County Executive Warren Evans's Sept. 25 veto of tax breaks for the Google data center in Van Buren Township.

    Oct 1, 2026

    ✅ Approved

    Van Buren Township's board voted 5-2 to approve 'Project Cannoli', a 1-gigawatt Google data center on 230 acres north of I-94 between Haggerty Road and I-275, despite residents' objections.

    Feb 11, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Google, DTE plan 1 gigawatt Michigan data center, eye Van Buren Township site · Planet Detroit · March 17, 2026
    2. Michigan regulators OK DTE contracts for Google data center · Michigan Public · Oct 2, 2026
    3. Google is considering a 1-gigawatt data center in Van Buren Township, near the Detroit airport · Bridge Michigan · Oct 8, 2026
    4. USGS aerial image of the land between Haggerty Road, I-94 and I-275 · USGS The National Map · Oct 8, 2026
    5. Township vote paves way for Michigan's second hyperscale data center · Bridge Michigan · Oct 14, 2026
    6. AG Nessel challenges MPSC approval of DTE's Google data center contracts · Michigan Department of Attorney General · Oct 30, 2026
    7. Michigan Data Centers: The Weekly Download · Michigan Advance · Nov 2, 2026
    8. Construction begins at Google hyperscale data center despite backlash · MLive (via Yahoo News) · Nov 15, 2026

    See something wrong? Tell us and we'll fix it.