No project in Oswego Township, but 7 nearby
Who decides here: the Kendall County Board usually decides on zoning in Oswego Township. Townships here have little say over land use.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Project Cardinal data center campus (Yorkville)
Yorkville, Kendall County
1,037 acres
🕒 June 9, 2026: Developer asked the city to move its land-purchase deadline from July 1, 2026 to Dec. 31…
Being builtabout 9 miles awayCyrusOne data center campus (Eldamain and Faxon roads, Yorkville)
Yorkville, Kendall County
228 acres
🕒 July 9, 2024: Yorkville City Council approved the CyrusOne campus and a development agreement.
Approved, not built yetabout 9 miles awayProject Steel data center campus (Yorkville)
Yorkville, Kendall County
550 acres
🕒 March 2026: Yorkville City Council approved annexation, a planned development and a development agre…
Reported in the news, not confirmed yet
Stopped or cancelledabout 10 miles awayKaris Critical data center at former Lucent campus (Naperville)
Naperville, DuPage County
🕒 Jan 20, 2026: Naperville City Council voted 6-1 to deny the data center after months of debate and a p…
Proposedabout 11 miles awayPlano Skies data center campus (Savion, off Rock Creek Road)
Plano, Kendall County
🕒 2026: Savion showed City Council a plan adding data center buildings to its solar project; ald…
Reported in the news, not confirmed yet
Approved, not built yetabout 13 miles awayHut 8 data center (1780 Hubbard Ave., Batavia)
Batavia, Kane County
🕒 Sept 2, 2025: City Council approved a water deal 9-2 that caps average use at 1,000 gallons a day and …
Being builtabout 14 miles awayEquinix data center campus north of Minooka (Ridge and Holt roads)
Minooka, Grundy County
368 acres
🕒 April 2026: Equinix donated land north of I-80 for a new fire station.
What you can do
- Get told first.
We'll email you if anything changes in Oswego Township. - Go to township meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Oswego Township: Commonwealth Edison Co. (company) or Ameren Illinois Company (company).