Approved, not built yetBig (AI-size): 1,800 megawatts

Project Cardinal data center campus (Yorkville)

Also called: Project Cardinal

Pioneer Development wants to build 14 two-story data center buildings on about 1,037 acres of farmland on Yorkville's north side. Yorkville approved it in November 2025. The water deal caps average use at 42,000 gallons a day. Neighbors have sued.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Yorkville City.

Where things stand: Approved, not built yet City Council approved the plan in Nov. 2025. In June 2026 the developer asked for more time (to Dec. 31, 2027) to buy the land. A neighbor's lawsuit is in court.

❓ 5 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (June 9, 2026): Developer asked the city to move its land-purchase deadline from July 1, 2026 to Dec. 31, 2027.

What we know

  • 📍 WhereNorthwest of Route 47 and Galena Road, south of Baseline Road, east of Ashe Road, Yorkville, Kendall County
  • 🏢 CompanyPioneer Development, LLC
  • 🌳 Size1,037 acres
  • ⚡ Power it needs1,800 megawatts (about as much as 1,440,000 homes)
  • 🔌 Where the power comes fromPlans include two electrical substations and a utility switchyard on site.
  • 🗼 New power linesYes
  • 💧 Water42,000 gallons a day
  • 💸 Tax breaksDeveloper agreed to pay the city $51 million up front over four years, if it buys the land. Backers project $35-70 million a year in property taxes for Yorkville schools at full build-out.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Which company will use the data centers? 🙋 I'll find out ·
  • Did the City Council grant the land-purchase extension to Dec. 31, 2027? 🙋 I'll find out ·
  • Where does the 1,800 megawatts of power come from, and who pays for the new power lines? 🙋 I'll find out ·
  • How did the court rule on the neighbor's lawsuit? 🙋 I'll find out ·
  • Did city officials sign an agreement to keep the plans private (NDA)? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: OpenStreetMap maps the Project Cardinal construction area north of Galena Road and west of Route 47, matching the news description. The pin is the centre of that area.

    What happened so far

    • June 10, 2025
      City Council held a public hearing on annexing part of the land.
    • Oct 28, 2025
      City Council put off (tabled) the vote.
    • Nov 10, 2025
      City Council voted unanimously to approve the campus plan.
    • Dec 2025
      A neighbor sued the city and the developer, saying the plan breaks the city's land-use plan for homes.
    • June 9, 2026
      Developer asked the city to move its land-purchase deadline from July 1, 2026 to Dec. 31, 2027.

    Local votes and rules

    ✅ Approved

    City council unanimously approved the 1,037-acre Project Cardinal data center campus (14 buildings) north of Galena Road. Buildings are limited to 78 feet. They must sit 625 feet from Bristol Bay homes and 1,200 feet from Equestrian Estates.

    Nov 10, 2025

    ⚖️ Court case

    A neighbor sued the city and developer Pioneer Development over Project Cardinal. The suit says the data center departs too far from the city plan, which marks the area for homes.

    Nov 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Project Cardinal Data Center Campus (case PZC 2025-08) · City of Yorkville · 2026
    2. Yorkville OKs 1,037-acre Project Cardinal data center · Shaw Local (Kendall County Now) · Nov 11, 2025
    3. Court sets schedule in lawsuit challenging Yorkville data center plan · WSPY News · Dec 2025
    4. Developers of Project Cardinal data center in Yorkville ask for 18-month extension to purchase land · Shaw Local (Kendall County Now) · June 8, 2026
    5. Data Centers in Illinois (1.8 GW figure) · Data Center Census · 2026
    6. Project Cardinal (landuse=construction, industrial=data_centre) · OpenStreetMap · Oct 8, 2026
    7. Sentinel-2 cloudless 2024 satellite image of the site · EOX / Copernicus Sentinel-2 · Oct 8, 2026

    See something wrong? Tell us and we'll fix it.