Being built
Equinix data center campus north of Minooka (Ridge and Holt roads)
Also called: Equinix CH8
Equinix is building seven data center buildings on about 368 acres north of Minooka, including an AI campus of four large buildings. It uses dry cooling, which saves water but uses more power. Full opening was planned for about 2031.
Where things stand: Village trustees approved it in Sept. 2025. Dirt work began around the end of 2025; the village says it is under construction.
๐ Latest update (April 2026): Equinix donated land north of I-80 for a new fire station.
What we know
- ๐ WhereNortheast corner of Ridge Road and Holt Road, north of I-80, Minooka, Grundy County
- ๐ข CompanyEquinix
- ๐ณ Size368 acres
- โ๏ธ Coolingdry cooling system (uses little water but more electricity)
- ๐ธ Tax breaksEquinix pays for road work and a bike path; village created a special service area for the campus.
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How many megawatts will the campus use? ๐ I'll find out
- Reports give $2 billion and $6 billion as the cost. Which is right? ๐ I'll find out
- Will there be diesel backup generators, and how many? ๐ I'll find out
What happened so far
- Sept 2025Minooka Village Board approved the Equinix campus after a public hearing.
- April 2026Equinix donated land north of I-80 for a new fire station.
๐ฐ๏ธ See it from above
An aerial photo of the area.
Photos: USGS The National Map.
Where this comes from
- Progress update on Equinix data center in Minooka ยท WCSJ / WSPY News ยท Sept 29, 2025
- Minooka Data Center FAQ and Fact Sheet ยท Village of Minooka ยท July 30, 2026
- Equinix donates land north of I-80 for new Minooka fire station ยท Shaw Local (Morris Herald-News) ยท April 21, 2026
See something wrong? Tell us and we'll fix it.