Approved, not built yetBig (AI-size): 550 acres

Project Steel data center campus (Yorkville)

Also called: Project Steel

A 550-acre data center campus with about 16 buildings is planned on farmland west of Eldamain Road. It would be built in three phases over about 20 years. The city says it will use about 25,000 gallons of water a day, up to 42,500 on peak days.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Yorkville City.

Where things stand: Approved, not built yet City Council approved annexation, zoning and a development deal in March 2026. First phase could start in summer 2027.

❓ 5 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (March 2026): Yorkville City Council approved annexation, a planned development and a development agreement.

What we know

  • 📍 WhereSouth of Galena Road and west of Eldamain Road, Yorkville, Kendall County
  • 🏢 CompanyPrologis
  • 🌳 Size550 acres
  • 🔌 Where the power comes fromPlans include three electrical substations.
  • 💧 Water25,000 gallons a day
  • 💸 Tax breaksDeveloper agreed to $40 million in up-front fees, mostly for Yorkville School District 115.
  • 👷 Jobs promised500

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How many megawatts of power will the campus use? 🙋 I'll find out ·
  • Which company will use the data centers? 🙋 I'll find out ·
  • Sources disagree on the number of buildings (16, 18 or 24). How many are planned? 🙋 I'll find out ·
  • Did city officials sign an agreement to keep the plans private (NDA)? 🙋 I'll find out ·
  • Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: news reports put the campus south of Galena Road and west of Eldamain Road. The pin is in that corner area.

    What happened so far

    • March 2026
      Yorkville City Council approved annexation, a planned development and a development agreement.

    Local votes and rules

    ✅ Approved

    City council unanimously approved the 1,037-acre Project Cardinal data center campus (14 buildings) north of Galena Road. Buildings are limited to 78 feet. They must sit 625 feet from Bristol Bay homes and 1,200 feet from Equestrian Estates.

    Nov 10, 2025

    ⚖️ Court case

    A neighbor sued the city and developer Pioneer Development over Project Cardinal. The suit says the data center departs too far from the city plan, which marks the area for homes.

    Nov 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. City Council gives green light to 550-acre data center campus · WSPY News · March 2026
    2. Developers of Project Cardinal ... (mentions Project Steel's $40 million agreement) · Shaw Local (Kendall County Now) · June 8, 2026
    3. Prologis Project Steel (listing) · Data Center Map · 2026
    4. Sentinel-2 cloudless 2024 satellite image of the site · EOX / Copernicus Sentinel-2 · Oct 8, 2026

    See something wrong? Tell us and we'll fix it.