1 data center project in South Elgin Village
Who decides here: the Village Board of South Elgin Village votes on zoning. The Kane County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Compass Datacenters campus at former Sears headquarters (Hoffman Estates)
Hoffman Estates, Cook County
273 acres
🕒 Dec 2025: Village issued permits; walls for the first two data center buildings went up.
Approved, not built yetabout 9 miles awayHut 8 data center (1780 Hubbard Ave., Batavia)
Batavia, Kane County
🕒 Sept 2, 2025: City Council approved a water deal 9-2 that caps average use at 1,000 gallons a day and …
Stopped or cancelledabout 10 miles awayPlum Farms rezoning for possible data center (Higgins Road and Route 59)
Hoffman Estates, Cook County
186 acres
🕒 June 30, 2026: Landowner withdrew its rezoning request after more than 3,250 people signed a petition a…
Stopped or cancelledabout 12 miles awayBrennan data center campus (Barrington Hills, south of Penny Road)
Barrington Hills, Cook County
🕒 Jan 28, 2026: Brennan withdrew its $2 billion data center plan and cancelled a planned public presenta…
Approved, not built yetabout 15 miles awayNexstar data center campus at WGN radio transmitter site (Rohlwing Road)
Elk Grove Village, Cook County
35 acres
🕒 Jan 2026: Village Board extended the deadline to start the first building to Sept. 30, 2027; the p…
Reported in the news, not confirmed yet
Local votes and rules
⏸️ Pause on new data centers
Village board unanimously approved a 12-month pause on building data centers while staff study their effects. It came after the board turned down a data center plan on Kenyon Road in August.
What you can do
- Get told first.
We'll email you if anything changes in South Elgin Village. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Commonwealth Edison Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Illinois.
🙋 Open tasks here
- On what date did the Village Board vote, and has the developer sued or gone to Kane County instead?