USA › Georgia › Fulton County › Union City City

5 data center projects in Union City City

Who decides here: the City Council of Union City City votes on zoning. The Fulton County may review big projects too.

Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.

In Union City City

Nearby (within 15 miles)

Proposedabout 2 miles away

Stonewall Tell data center (RSC Investment Management)

South Fulton, Fulton County

59 acres

🕒 Dec 6, 2024: RSC filed a 1.9 million square foot data center for state regional review (DRI #4342).

Proposedabout 2 miles away

Vantage data center (Stacks Road site, South Fulton)

South Fulton, Fulton County

🕒 Aug 13, 2024: Vantage filed a 697,000 square foot data center for state regional review (DRI #4257).

Proposedabout 5 miles away

Fairburn Technology Center (Bohannon Drive)

Fairburn, Fulton County

59.6 acres

🕒 May 22, 2024: Three data center buildings (1.19 million square feet) filed for state regional review (…

Approved, not built yetabout 5 miles away

Microsoft data center (Project Rita, Tyrone)

Tyrone, Fayette County

161 acres · for Microsoft

🕒 Aug 6, 2026: Town staff presented a review of data center rules to the council.

Proposedabout 6 miles away

T5 ATL IV data center campus (Gullatt Road, Fairburn)

Fairburn, Fulton County

91 acres

🕒 May 5, 2025: T5 filed T5 ATL IV for state regional review (DRI #4465): up to 2.2 million square feet.

Proposedabout 8 miles away

Vantage data center (Westlake site, South Fulton)

South Fulton, Fulton County

🕒 Aug 13, 2024: Vantage filed a 754,000 square foot data center for state regional review (DRI #4256).

Stopped or cancelledabout 9 miles away

Project Peach data center campus (CyrusOne)

Unincorporated Coweta County, Coweta County

320 acres

🕒 Oct 20, 2026: Coweta County commissioners approved turning the Project Peach land (rezoning case REZON…

Proposedabout 9 miles away

T5 ATL IV data center (Coweta County site)

Unincorporated Coweta County, Coweta County

200 acres

🕒 Oct 12, 2026: The county said a public hearing on rezoning the 200-acre Project Pegasus site is set fo…

Local votes and rules

📜 Data center rules

Union City council approved, in a split vote, adding data centers as a conditional use in its office-industrial zoning district, over many residents' objections. The city already allowed data centers in other districts, including Microsoft's large project.

Feb 2025Source
Built & runningBeing builtApproved, not built yetProposedStopped or cancelledHollow dot (when zoomed in): exact site not known yet, pin shows the town

What you can do

  1. Get told first.
    We'll email you if anything changes in Union City City.
  2. Go to council meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
📣 Report something here

🔔 Get told first

We'll email you when something changes in Union City City. Nothing else.

⚡ Your electric company

Depending on where you live in Union City City: Georgia Power Co. (company) or Greystone Power Corporation (co-op (owned by its members)).

Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Georgia.

🙋 Open tasks here

  • What tax break did the Development Authority of Fulton County approve?
  • How much power will it use?
  • Is construction under way?
  • How much power and water will it use?
  • Is ATL50 part of the Microsoft campus already planned nearby?
  • Who is behind Burr Computer Environments?
  • Is this the same project as the Microsoft campus on Stonewall Tell Road?
  • Is it under construction?
  • Has the city approved it, and has construction started?
  • How much power will it use?
  • How much power will it need, and who will supply it?
  • How much water will it use per day, and what cooling system will it have?
  • Who is the end user (tenant)?
  • Is this the same project as the earlier 'The Crossings' filing (DRI #4617), which was terminated?
  • When will Union City review the master plan, and will there be a public hearing?
  • Did any official sign an agreement to keep the plans private (NDA)?