2 data center projects in Fairburn City
Who decides here: the City Council of Fairburn City votes on zoning. The Fulton County may review big projects too.
In Fairburn City
T5 ATL IV data center campus (Gullatt Road, Fairburn)
Fairburn, Fulton County
91 acres
π May 5, 2025: T5 filed T5 ATL IV for state regional review (DRI #4465): up to 2.2 million square feet.
ProposedFairburn Technology Center (Bohannon Drive)
Fairburn, Fulton County
59.6 acres
π May 22, 2024: Three data center buildings (1.19 million square feet) filed for state regional review (β¦
Nearby (within 15 miles)
TA Realty ATL03 / Red Oak data center
Union City, Fulton County
67.8 acres
π Oct 31, 2024: TA Realty filed four data center buildings (about 1 million square feet) for state regioβ¦
Proposedabout 3 miles awayATL11 data center (Stonewall Tell Road)
Union City, Fulton County
π July 15, 2024: A 2.1 million square foot data center was filed for state regional review (DRI #4235).
Approved, not built yetabout 4 miles awayMicrosoft Union City data center campus (Stonewall Tell Road)
Union City, Fulton County
136 acres Β· for Microsoft
π April 2024: Microsoft bought 136 acres in Fulton County for $53.5 million.
Reported in the news, not confirmed yet
Proposedabout 4 miles awayMicrosoft ATL50 data center
Union City, Fulton County
88.01 acres Β· for Microsoft
π Sept 15, 2026: Union City filed Microsoft's ATL50 for state regional review (DRI #4843): two 3-story buβ¦
Approved, not built yetabout 5 miles awayMicrosoft data center (Project Rita, Tyrone)
Tyrone, Fayette County
for Microsoft
π Aug 6, 2026: Town staff presented a review of data center rules to the council.
Proposedabout 5 miles awayStonewall Tell data center (RSC Investment Management)
South Fulton, Fulton County
59 acres
π Dec 6, 2024: RSC filed a 1.9 million square foot data center for state regional review (DRI #4342).
What you can do
- Get told first.
We'll email you if anything changes in Fairburn City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Depending on where you live in Fairburn City: Georgia Power Co. (company) or City of Fairburn (not available) or Coweta-fayette El Member Corp. (co-op (owned by its members)) or Greystone Power Corporation (co-op (owned by its members)).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Georgia.
π Open tasks here
- Who is the end user?
- Did it get a tax break?
- Has Fairburn approved it?
- Who is the end user?
- How much power will it use?