3 data center projects in Unincorporated Floyd County
Who decides here: the Floyd County Board of Commissioners decides on zoning for land outside city and town limits.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
In Unincorporated Floyd County
Microsoft data center (Huffaker Road, Rome area)
Unincorporated Floyd County, Floyd County
349 acres · for Microsoft
🕒 Oct 20, 2026: Floyd County filed a state regional review (DRI #4860, 'ATL80') for Microsoft's data cen…
ProposedCoosa data center campus (Project Gracie, Atlas Development)
Unincorporated Floyd County, Floyd County
200 acres
🕒 May 1, 2025: Atlas filed Project Gracie for state regional review (DRI #4448): seven buildings, 2.4 m…
Stopped or cancelledDixon data center (Atlas Development)
Unincorporated Floyd County, Floyd County
178 acres
🕒 Feb 6, 2025: Atlas withdrew its request to rezone 178 acres for a data center of more than 2 million …
Reported in the news, not confirmed yet
Nearby (within 15 miles)
Battey Business Complex data center (Atlas Development)
Rome, Floyd County
100 acres
🕒 Aug 2026: Atlas ended the agreement; no reason was given.
Reported in the news, not confirmed yet
Proposedabout 15 miles awayProject Springbank (Atlas Development)
Unincorporated Bartow County, Bartow County
630 acres
🕒 Feb 14, 2025: Atlas Development's six-building, 2.27 million square foot campus was filed for state re…
Local votes and rules
📜 Data center rules
Floyd County approved new rules for future data centers outside Rome's city limits. They are allowed only in heavy industrial zones and must meet rules on noise, water and power use, safety and cleanup. Breaking the rules can mean fines of up to $1,000 a day.
What you can do
- Get told first.
We'll email you if anything changes in Unincorporated Floyd County. - Go to county meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Unincorporated Floyd County: Georgia Power Co. (company) or North Georgia Electric Member Corp. (co-op (owned by its members)).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Georgia.
🙋 Open tasks here
- Did the Floyd County Commission approve the rezoning on May 27, 2025?
- Will it really use 5 million gallons of water a day?
- How much power will it need?
- Where exactly on Huffaker Road is the site? A parcel number or map from the state filing helps.
- How many diesel backup generators will there be?
- The state filing gives a build-out value of $340 million; news in 2023 said $1 billion. Which is right?
- Does Microsoft need a rezoning or other county vote, and when is the hearing?
- Has Atlas refiled anywhere nearby?