Microsoft bought about 347 acres near Huffaker Road in Floyd County in 2023 for a data center. In October 2026 it filed state paperwork for 'ATL80': 3 buildings, up to 1.66 million square feet, about 422 megawatts of power at peak, and about 13,500 gallons of water a day at most. Full build-out is planned by 2032.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Floyd County Board of Commissioners (for land outside city and town limits).
Where things stand: Proposed Microsoft filed a state regional review (DRI #4860, 'ATL80') in October 2026 for 3 buildings on about 349 acres north of Huffaker Road. No construction permit found yet.
❓ 4 open questions about it: see below.
Last checked Oct 26, 2026.
🕒 Latest update (Oct 20, 2026): Floyd County filed a state regional review (DRI #4860, 'ATL80') for Microsoft's data center: 3 buildings, up to 1,659,000 sq ft on 349 acres, about 422 MW peak power, 150 jobs, finished by 2032.
What we know
- 📍 WhereNorth of Huffaker Road, unincorporated Floyd County, Unincorporated Floyd County, Floyd County
- 🏢 CompanyMicrosoft
- 🏛️ Owned byMicrosoft
- 👤 Built forMicrosoft
- 🌳 Size349 acres
- ⚡ Power it needs422 megawatts (about as much as 337,600 homes)
- 🔌 Where the power comes fromGeorgia Power, with a new substation on site and a power line extended to the site
- 🗼 New power linesYes
- 💧 WaterFloyd County water (Old Mill Spring and groundwater) · 13,500 gallons a day
- 💵 Cost$1 billion
- 👷 Jobs promised150
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Where exactly on Huffaker Road is the site? A parcel number or map from the state filing helps. 🙋 I'll find out ·
- How many diesel backup generators will there be? 🙋 I'll find out ·
- The state filing gives a build-out value of $340 million; news in 2023 said $1 billion. Which is right? 🙋 I'll find out ·
- Does Microsoft need a rezoning or other county vote, and when is the hearing? 🙋 I'll find out ·
🔎 What we checked
- Oct 26, 2026: We checked the state DRI filing: it lists backup diesel generators but not how many.
What happened so far
- Oct 2023Microsoft bought 347 acres near Huffaker Road for a data center, a $1 billion project.
- Oct 20, 2026Floyd County filed a state regional review (DRI #4860, 'ATL80') for Microsoft's data center: 3 buildings, up to 1,659,000 sq ft on 349 acres, about 422 MW peak power, 150 jobs, finished by 2032.
Local votes and rules
📜 Data center rules
Floyd County approved new rules for future data centers outside Rome's city limits. They are allowed only in heavy industrial zones and must meet rules on noise, water and power use, safety and cleanup. Breaking the rules can mean fines of up to $1,000 a day.
Drag the slider to compare the land before and now.
Where this comes from
- Data center planned on 114-acre plot in Rome, Georgia · Data Center Dynamics · 2024
- Microsoft to invest $1 billion in data center in Floyd County · Rome News-Tribune / MDJ · Oct 30, 2023
- DRI #4860: ATL80 · Georgia Department of Community Affairs · Oct 20, 2026
- DRI #4860: ATL80, Initial Information Form · Georgia Department of Community Affairs · Oct 20, 2026
- DRI #4860: ATL80, Information Form Part 2 · Georgia Department of Community Affairs · Oct 20, 2026
See something wrong? Tell us and we'll fix it.