Proposed

Project Springbank (Atlas Development)

Also called: Project Springbank

Atlas Development plans six data center buildings, about 2.3 million square feet, near Adairsville. The state filing values it at $4.5 billion and says it would use closed-loop cooling and about 15,000 gallons of water a day. It aims to be done by the end of 2031.

โœ” ConfirmedSourceLast checked: Oct 6, 2026

Where things stand: Filed for state review in Feb. 2025. We found no final county vote.

๐Ÿ•’ Latest update (Feb 14, 2025): Atlas Development's six-building, 2.27 million square foot campus was filed for state regional review (DRI #4403).

What we know

  • ๐Ÿ“ WhereSoutheast of Adairsville, along Perkins Mountain Road (based on the filing's map point, per DCD), Unincorporated Bartow County, Bartow County
  • ๐Ÿข CompanyAtlas Development LLC
  • ๐Ÿ’ง WaterBartow County ยท 15,000 gallons a day
  • โ„๏ธ Coolingclosed-loop system to reduce water use (per state filing)
  • ๐Ÿ’ต Cost$4.5 billion

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Feb 14, 2025
    Atlas Development's six-building, 2.27 million square foot campus was filed for state regional review (DRI #4403).

Local votes and rules

๐Ÿ“œ Data center rules

Bartow County finished a data center ordinance in January 2025. It allows data centers with a 200-foot buffer from the property line and noise limits: 65 decibels by day and 55 decibels at night. County leaders say they welcome data centers.

Jan 2025
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. DRI #4403: Project Springbank (Development of Regional Impact filing) ยท Georgia Department of Community Affairs ยท Feb 14, 2025
  2. DRI #4403: Project Springbank, Additional Information Form ยท Georgia Department of Community Affairs ยท Feb 14, 2025
  3. Two million sq ft data center campus planned outside Atlanta, Georgia ยท Data Center Dynamics ยท 2025

See something wrong? Tell us and we'll fix it.