Project Springbank (Atlas Development)
Also called: Project Springbank
Atlas Development plans six data center buildings, about 2.3 million square feet, near Adairsville. The state filing values it at $4.5 billion and says it would use closed-loop cooling and about 15,000 gallons of water a day. It aims to be done by the end of 2031.
Where things stand: Filed for state review in Feb. 2025. We found no final county vote.
๐ Latest update (Feb 14, 2025): Atlas Development's six-building, 2.27 million square foot campus was filed for state regional review (DRI #4403).
What we know
- ๐ WhereSoutheast of Adairsville, along Perkins Mountain Road (based on the filing's map point, per DCD), Unincorporated Bartow County, Bartow County
- ๐ข CompanyAtlas Development LLC
- ๐ง WaterBartow County ยท 15,000 gallons a day
- โ๏ธ Coolingclosed-loop system to reduce water use (per state filing)
- ๐ต Cost$4.5 billion
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How much power will it need? ๐ I'll find out
- Has Bartow County approved a rezoning? ๐ I'll find out
- Who is the end user? ๐ I'll find out
What happened so far
- Feb 14, 2025Atlas Development's six-building, 2.27 million square foot campus was filed for state regional review (DRI #4403).
Local votes and rules
๐ Data center rules
Bartow County finished a data center ordinance in January 2025. It allows data centers with a 200-foot buffer from the property line and noise limits: 65 decibels by day and 55 decibels at night. County leaders say they welcome data centers.
An aerial photo of the area.
Where this comes from
- DRI #4403: Project Springbank (Development of Regional Impact filing) ยท Georgia Department of Community Affairs ยท Feb 14, 2025
- DRI #4403: Project Springbank, Additional Information Form ยท Georgia Department of Community Affairs ยท Feb 14, 2025
- Two million sq ft data center campus planned outside Atlanta, Georgia ยท Data Center Dynamics ยท 2025