ProposedBig (AI-size): 630 acres

Project Springbank (Atlas Development)

Also called: Project Springbank

Atlas Development plans six data center buildings, about 2.3 million square feet, near Adairsville. The state filing values it at $4.5 billion and says it would use closed-loop cooling and about 15,000 gallons of water a day. It aims to be done by the end of 2031.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Bartow County Board of Commissioners (for land outside city and town limits).

Where things stand: Proposed Filed for state review in Feb. 2025. We found no final county vote.

❓ 3 open questions about it: see below.

Last checked Oct 10, 2026.

🕒 Latest update (Feb 14, 2025): Atlas Development's six-building, 2.27 million square foot campus was filed for state regional review (DRI #4403).

What we know

  • 📍 WhereSoutheast of Adairsville, along Perkins Mountain Road (based on the filing's map point, per DCD), Unincorporated Bartow County, Bartow County
  • 🏢 CompanyAtlas Development LLC
  • 🌳 Size630 acres
  • 💧 WaterBartow County · 15,000 gallons a day
  • ❄️ Coolingclosed-loop system to reduce water use (per state filing)
  • 💵 Cost$4.5 billion

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Feb 14, 2025
      Atlas Development's six-building, 2.27 million square foot campus was filed for state regional review (DRI #4403).

    Local votes and rules

    📜 Data center rules

    Bartow County finished a data center ordinance in January 2025. It allows data centers with a 200-foot buffer from the property line and noise limits: 65 decibels by day and 55 decibels at night. County leaders say they welcome data centers.

    Jan 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. DRI #4403: Project Springbank (Development of Regional Impact filing) · Georgia Department of Community Affairs · Feb 14, 2025
    2. DRI #4403: Project Springbank, Additional Information Form · Georgia Department of Community Affairs · Feb 14, 2025
    3. Two million sq ft data center campus planned outside Atlanta, Georgia · Data Center Dynamics · 2025
    4. New data center eyes Bartow · The Daily Tribune News · April 2, 2025

    See something wrong? Tell us and we'll fix it.