1 data center project in Lovejoy City

Who decides here: the City Council of Lovejoy City votes on zoning. The Clayton County may review big projects too.

Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.

In Lovejoy City

Nearby (within 15 miles)

Being builtabout 5 miles away

Equinix xScale data center campus (Hampton)

Hampton, Henry County

🕒 Jan 13, 2026: Equinix sold the Hampton data center campus to its xScale joint venture (AMER 3) for $45…

Approved, not built yetabout 5 miles away

Henderson Farms data center campus (Hampton)

Hampton, Henry County

133 acres

🕒 March 24, 2026: A larger Henderson Farms plan with a data center campus and training facility was filed …

Being builtabout 5 miles away

Hampton Technology Park

Hampton, Henry County

603.56 acres

🕒 July 2026: A cemetery group raised concerns that the project is close to the historic O'Neal AME Ch…

Proposedabout 6 miles away

Rocky Creek Road data center (Red Wolf DCD Properties)

Unincorporated Henry County, Henry County

148.2 acres

🕒 May 3, 2024: A 1.25 million square foot data center filed for state regional review (DRI #4198).

Proposedabout 7 miles away

Strickland Tract data center (Red Wolf DCD Properties)

Unincorporated Henry County, Henry County

249.8 acres

🕒 July 31, 2024: A 1.25 million square foot data center filed for state regional review (DRI #4251).

Stopped or cancelledabout 9 miles away

Highway 85 North data center (Crow Holdings)

Fayetteville, Fayette County

37.4 acres

🕒 March 18, 2026: The developer withdrew its appeal, one day before the City Council hearing.

Reported in the news, not confirmed yet

Proposedabout 11 miles away

QTS ATL2 East data center

Fayetteville, Fayette County

313 acres

🕒 April 21, 2026: The regional commission issued its finding on the project.

Local votes and rules

🚫 Ban

Lovejoy passed an ordinance that bans data centers anywhere in the city. It followed months of opposition to a planned 3.5 million square foot data center campus on Panhandle Road near two schools. That developer had already withdrawn and plans homes on the site instead.

Sept 28, 2026Source

📌 Other

At a city council meeting, Stillwater Development formally withdrew its plan for a 15-building, 1.25-gigawatt data center campus at 11760 Panhandle Road. The city had warned about school traffic near the site.

Aug 6, 2026Source
Built & runningBeing builtApproved, not built yetProposedStopped or cancelledHollow dot (when zoomed in): exact site not known yet, pin shows the town

What you can do

  1. Get told first.
    We'll email you if anything changes in Lovejoy City.
  2. Go to council meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
📣 Report something here

🔔 Get told first

We'll email you when something changes in Lovejoy City. Nothing else.

⚡ Your electric company

Georgia Power Co. (company).