5 data center projects in Unincorporated Mecklenburg County
Who decides here: the Mecklenburg County Board of Supervisors decides on zoning for land outside city and town limits.
In Unincorporated Mecklenburg County
Microsoft data center campuses in Mecklenburg County
Mecklenburg County, Mecklenburg County
for Microsoft
π June 2024: Microsoft agreed to pay a $41,766.90 fine to the state for destroying 2.33 acres of wetlβ¦
ProposedMicrosoft AVC22 campus expansion at Lakeside Commerce Park
Mecklenburg County, Mecklenburg County
490 acres Β· for Microsoft
π June 2026: Microsoft filed plans for a 490-acre campus with three buildings and a substation next tβ¦
Reported in the news, not confirmed yet
Status unclearMicrosoft six-building campus off Butler Farm Road
Mecklenburg County, Mecklenburg County
369 acres Β· for Microsoft
π April 2023: Microsoft applied to the U.S. Army Corps of Engineers for a six-building campus that wouβ¦
Reported in the news, not confirmed yet
Status unclearMicrosoft Hillcrest campus on Tunstall Road
Mecklenburg County, Mecklenburg County
132 acres Β· for Microsoft
π 2021: Microsoft asked for a zoning change for the site.
Reported in the news, not confirmed yet
Being builtTECfusions Clarksville data center and expansion
Mecklenburg County, Mecklenburg County
73 acres
π Feb 24, 2025: TECfusions said it bought and rezoned 73 acres to add 300 megawatts for AI computing.
Reported in the news, not confirmed yet
What you can do
- Get told first.
We'll email you if anything changes in Unincorporated Mecklenburg County. - Go to county meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Depending on where you live in Unincorporated Mecklenburg County: Mecklenburg Electric Cooperative (co-op (owned by its members)) or Virginia Electric & Power Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Virginia.
π Open tasks here
- How much water do Microsoft's Mecklenburg data centers use per day?
- How many diesel generators do Microsoft's Mecklenburg sites have?
- How many streams and wetlands would the AVC22 campus affect?
- How much power will AVC22 use?
- Is Microsoft's Butler Farm Road campus under construction?
- Did the Army Corps approve the wetlands permit for the Butler Farm Road campus?
- Is the Hillcrest campus on Tunstall Road running yet?
- Which local body approved the TECfusions rezoning, and when?
- How much water will the TECfusions expansion use?