๐Ÿ“ฃ Report Something
Being built

TECfusions Clarksville data center and expansion

TECfusions runs a data center in an old factory building on Burlington Drive in Clarksville. It plans to add 300 megawatts on 73 more acres for AI customers. One parcel is set aside for housing.

๐Ÿ‘ฅ Reported, not confirmed yetSourceLast checked: Oct 7, 2026

Where things stand: The first building runs and is fully leased. In 2025 TECfusions bought and rezoned 73 more acres to add 300 megawatts.

๐Ÿ•’ Latest update (Feb 24, 2025): TECfusions said it bought and rezoned 73 acres to add 300 megawatts for AI computing.

What we know

  • ๐Ÿ“ Where250 Burlington Drive, just outside the town of Clarksville, Mecklenburg County, Mecklenburg County
  • ๐Ÿข CompanyTECfusions
  • ๐ŸŒณ Size73 acres
  • โšก Power it needs300 megawatts (about as much as 240,000 homes)
  • ๐Ÿ”Œ Where the power comes fromPlans to reuse old 138-kilovolt power lines from a closed coal plant

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Feb 24, 2025
    TECfusions said it bought and rezoned 73 acres to add 300 megawatts for AI computing.
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. TECfusions acquires 73 acres in Virginia for data center expansion project ยท Lightwave ยท Feb 25, 2025
  2. Census geocoder: 250 Burlington Dr, Clarksville, VA ยท U.S. Census Bureau ยท Oct 7, 2026

See something wrong? Tell us and we'll fix it.