Status unclearBig (AI-size): 132 acres

Microsoft Hillcrest campus on Tunstall Road

Also called: AVC09, Hillcrest Site Data Center

Microsoft planned three data center buildings and a substation on 132 acres at 210 Tunstall Road, with about 48 megawatts in total.

👥 Reported, not confirmed yetSourceLast checked: Oct 7, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Mecklenburg County Board of Supervisors (for land outside city and town limits).

Where things stand: Status unclear Planned to finish in 2024, but a tracker still lists it as proposed. Current stage not confirmed.

❓ 1 open question about it: see below.

Last checked Oct 7, 2026.

🕒 Latest update (2021): Microsoft asked for a zoning change for the site.

What we know

  • 📍 Where210 Tunstall Road, Mecklenburg County, Mecklenburg County
  • 🏢 CompanyMicrosoft
  • 👤 Built forMicrosoft
  • 🌳 Size132 acres
  • ⚡ Power it needs48 megawatts (about as much as 38,400 homes)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Is the Hillcrest campus on Tunstall Road running yet? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • 2020
      Microsoft bought the Tunstall Road land.
    • 2021
      Microsoft asked for a zoning change for the site.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Microsoft To Develop a Data Center Campus in Mecklenburg County, Virginia · Baxtel · July 19, 2022
    2. Microsoft Hillcrest Data Center (AVC09) · More Than Just Parks Data Center Tracker · Sept 2025

    See something wrong? Tell us and we'll fix it.