Microsoft six-building campus off Butler Farm Road
Also called: LYH03 Bailey
Microsoft asked for permits to build six data centers on 369 acres of fields and woods. The plan would wipe out more than 5,000 feet of streams and wetlands.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Mecklenburg County Board of Supervisors (for land outside city and town limits).
Where things stand: Status unclear Filed for a federal wetlands permit in 2023. One tracker lists a six-building Microsoft campus as under construction, but we found no local confirmation.
❓ 2 open questions about it: see below.
Last checked Oct 7, 2026.
🕒 Latest update (April 2023): Microsoft applied to the U.S. Army Corps of Engineers for a six-building campus that would fill over 5,000 feet of streams and wetlands.
What we know
- 📍 WhereWest of Skipwith Road and north of Butler Farm Road, Mecklenburg County, Mecklenburg County
- 🏢 CompanyMicrosoft
- 👤 Built forMicrosoft
- 🌳 Size369 acres
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Is Microsoft's Butler Farm Road campus under construction? 🙋 I'll find out ·
- Did the Army Corps approve the wetlands permit for the Butler Farm Road campus? 🙋 I'll find out ·
What happened so far
- April 2023Microsoft applied to the U.S. Army Corps of Engineers for a six-building campus that would fill over 5,000 feet of streams and wetlands.
Drag the slider to compare the land before and now.
Where this comes from
- Microsoft Submits Plans For a Six-Building Data Center Facility in Mecklenburg County, Virginia · Baxtel · April 12, 2023
- Microsoft Azure Boydton Phase 11 · More Than Just Parks Data Center Tracker · Jan 15, 2026