πŸ“£ Report Something
USA β€Ί Virginia β€Ί King George County β€Ί Unincorporated King George County

2 data center projects in Unincorporated King George County

Who decides here: the King George County Board of Supervisors decides on zoning for land outside city and town limits.

In Unincorporated King George County

Local votes and rules

βš–οΈ Court case

Amazon Data Services sued after the county zoning appeals board upheld a refusal to confirm Amazon's 'vested rights' to build on the 893-acre Birchwood site. A trial was scheduled for September 28-29, 2026; no ruling had been reported.

April 24, 2024Source

πŸ“Œ Other

A newly elected board majority canceled the tax deal (performance agreement) the county had signed with Amazon on December 19, 2023 for an 869-acre data center campus at the old Birchwood power plant, and began looking at rezoning the land back to farmland.

Jan 2, 2024Source
Built & runningBeing builtApproved, not built yetProposedStopped or cancelled

What you can do

  1. Get told first.
    We'll email you if anything changes in Unincorporated King George County.
  2. Go to county meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
πŸ“£ Report something here

πŸ”” Get told first

We'll email you when something changes in Unincorporated King George County. Nothing else.

⚑ Your electric company

Depending on where you live in Unincorporated King George County: Virginia Electric & Power Co. (company) or Northern Neck Electric Co-op, Inc. (co-op (owned by its members)).

Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Virginia.

πŸ™‹ Open tasks here

  • Who will use the campus?
  • Where will cooling water come from?
  • Who will use it, and where will its power come from?

How to help β†’