King George Technology Center (Green Energy Ventures)
King George County, King George County
300 acres
π Feb 17, 2026: Board of Supervisors approved the rezoning 3-2 and a height permit.
Reported in the news, not confirmed yet
Approved, not built yetDahlgren West data center campus (Oasis Digital Properties)
King George County, King George County
485 acres
π Aug 2025: Board of Supervisors approved the campus unanimously.
Reported in the news, not confirmed yet
Local votes and rules
βοΈ Court case Β· King George County
Amazon Data Services sued after the county zoning appeals board upheld a refusal to confirm Amazon's 'vested rights' to build on the 893-acre Birchwood site. A trial was scheduled for September 28-29, 2026; no ruling had been reported.
π Other Β· King George County
A newly elected board majority canceled the tax deal (performance agreement) the county had signed with Amazon on December 19, 2023 for an 869-acre data center campus at the old Birchwood power plant, and began looking at rezoning the land back to farmland.