Approved, not built yetBig (AI-size): 300 acres

King George Technology Center (Green Energy Ventures)

Supervisors rezoned about 300 acres at Route 3 and Bloomsbury Road for 13 data center buildings, 6.5 million square feet in all. Groundwater may not be used to cool equipment, and only the cleanest (Tier 4) generators are allowed. Buildings may be up to 90 feet tall.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the King George County Board of Supervisors (for land outside city and town limits).

Where things stand: Approved, not built yet Supervisors approved the rezoning 3-2 in February 2026.

❓ 3 open questions about it: see below.

Last checked Oct 10, 2026.

🕒 Latest update (Feb 17, 2026): Board of Supervisors approved the rezoning 3-2 and a height permit.

What we know

  • 📍 WhereNorthwest corner of Kings Highway (Route 3) and Bloomsbury Road, King George County, King George County
  • 🏢 CompanyGreen Energy Ventures
  • 🌳 Size300 acres
  • 💧 Watertemporary wells for drinking water at first; King George Service Authority later

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Who will use the campus? 🙋 I'll find out ·
  • Where will cooling water come from? 🙋 I'll find out ·
  • Is the approved King George Technology Center site about 300 acres or 352 acres? Earlier plans said 352 acres. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Feb 17, 2026
      Board of Supervisors approved the rezoning 3-2 and a height permit.

    Local votes and rules

    ⚖️ Court case

    Amazon Data Services sued after the county zoning appeals board upheld a refusal to confirm Amazon's 'vested rights' to build on the 893-acre Birchwood site. A trial was scheduled for September 28-29, 2026; no ruling had been reported.

    April 24, 2024

    📌 Other

    A newly elected board majority canceled the tax deal (performance agreement) the county had signed with Amazon on December 19, 2023 for an 869-acre data center campus at the old Birchwood power plant, and began looking at rezoning the land back to farmland.

    Jan 2, 2024
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. King George Board of Supervisors approves 300-acre data center campus · Fredericksburg Free Press · Feb 19, 2026
    2. Green Energy Ventures Presents its Plan for the King George Technology Center · FXBG Advance

    See something wrong? Tell us and we'll fix it.