Projects
Remington Technology Park (Lucky Hill Road)
Fauquier County, Fauquier County
234 acres
🕒 Oct 8, 2026: County staff told supervisors that Remington Technology Park was approved and is under c…
Reported in the news, not confirmed yet
Stopped or cancelledGigaland data center (Remington)
Fauquier County, Fauquier County
200 acres
🕒 Aug 17, 2026: Developer withdrew again before the September hearing.
Reported in the news, not confirmed yet
Status unclearAmazon data center on Blackwell Road (Warrenton)
Warrenton, Fauquier County
42 acres · for Amazon Web Services
🕒 July 30, 2026: Judge denied a residents' group's request to join Amazon's appeal.
Stopped or cancelledConvergent Technology Park (south of Remington)
Fauquier County, Fauquier County
100 acres
🕒 Aug 27, 2026: Developer withdrew the rezoning.
Local votes and rules
🗺️ Zoning change · Fauquier County
Supervisors voted 4-1 to allow new data centers only in planned commercial industrial (PCID) zones, with a special exception. Business park zones no longer allow them. Projects already approved or in process are not affected.
✅ Approved · Fauquier County
Supervisors voted to let Remington Technology Park, a six-building data center project in Remington, power itself with an on-site plant of 488 natural gas fuel cells instead of 13 gas turbines.
🗺️ Zoning change · Warrenton
Town council voted 6-0 to strike data centers as an allowed use in industrial zones. It does not cancel the special use permit the town gave Amazon in February 2023 for a data center on Blackwell Road.
✋ Turned down · Fauquier County
The county planning commission voted 4-1 to recommend denial of 'Gigaland', a seven-building, 2.2-million-square-foot data center campus in Remington. The developers later withdrew the application, cancelling a September 11, 2025 supervisors' hearing, and said they would file a new one.
⚖️ Court case · Warrenton
The nonprofit Citizens for Fauquier County and town residents sued to overturn the town council's February 2023 special use permit for a 220,000-square-foot Amazon data center on Blackwell Road. A trial was held in March 2026 and final arguments were on June 15, 2026; no ruling had been reported.
Find your town
In Virginia, cities and towns decide inside their limits. Outside them, the county decides.