No project in Coupland City, but 7 nearby
Who decides here: the City Council of Coupland City votes on zoning. The Williamson County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
KDC 'Project Comal' data center campus (Taylor)
Taylor, Williamson County
220 acres
🕒 March 26, 2026: Taylor City Council voted unanimously to annex and zone the land for the data center.
Reported in the news, not confirmed yet
Approved, not built yetabout 8 miles awayBlueprint data center campus (MLK Jr. Drive, Taylor)
Taylor, Williamson County
🕒 Oct 2025: A state district judge dismissed a lawsuit against Blueprint.
Being builtabout 10 miles awaySkybox PowerCampus Austin (Hutto)
Hutto, Williamson County
220 acres
🕒 Nov 2023: State filing for the first Hutto building; construction set for Jan. to Nov. 2024.
Reported in the news, not confirmed yet
Approved, not built yetabout 11 miles awaySkybox 'Project Sequel' data center campus (Hutto Megasite)
Hutto, Williamson County
140 acres
🕒 Oct 2026: Hutto City Council voted 6-0 to rezone the 140-acre Megasite tract as a planned developm…
Reported in the news, not confirmed yet
Stopped or cancelledabout 12 miles awayZydeco 'Project Hutto' data center (Ed Schmidt Blvd, Hutto)
Hutto, Williamson County
🕒 April 2026: Zydeco withdrew its rezoning request; the special Planning and Zoning meeting set for Ap…
Reported in the news, not confirmed yet
Approved, not built yetabout 12 miles awayColovore 'Project Raptor' data center (Hutto)
Hutto, Williamson County
🕒 Dec 2024: Hutto City Council granted a site use permit for the data center.
Reported in the news, not confirmed yet
What you can do
- Get told first.
We'll email you if anything changes in Coupland City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Coupland City: Oncor Electric Delivery Company LLC (company) or City of Bartlett (not available) or Pedernales Electric Co-op, Inc. (co-op (owned by its members)) or Bluebonnet Electric Co-op, Inc. (co-op (owned by its members)) or Bartlett Electric Co-op, Inc. (co-op (owned by its members)).
In much of Texas you can pick who sells you power, but this company owns the power lines.
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Texas.