No project in Coupland City, but 6 nearby
Who decides here: the City Council of Coupland City votes on zoning. The Williamson County may review big projects too.
Nearby (within 15 miles)
Blueprint data center campus (MLK Jr. Drive, Taylor)
Taylor, Williamson County
π Oct 2025: A state district judge dismissed a lawsuit against Blueprint.
Approved, not built yetabout 8 miles awayKDC 'Project Comal' data center campus (Taylor)
Taylor, Williamson County
220 acres
π March 26, 2026: Taylor City Council voted unanimously to annex and zone the land for the data center.
Reported in the news, not confirmed yet
Being builtabout 10 miles awaySkybox PowerCampus Austin (Hutto)
Hutto, Williamson County
220 acres
π Nov 2023: State filing for the first Hutto building; construction set for Jan. to Nov. 2024.
Reported in the news, not confirmed yet
Stopped or cancelledabout 11 miles awayZydeco 'Project Hutto' data center (Ed Schmidt Blvd, Hutto)
Hutto, Williamson County
π April 2026: Zydeco withdrew its rezoning request; the special Planning and Zoning meeting set for Apβ¦
Reported in the news, not confirmed yet
Approved, not built yetabout 12 miles awayColovore 'Project Raptor' data center (Hutto)
Hutto, Williamson County
π Dec 2024: Hutto City Council granted a site use permit for the data center.
Reported in the news, not confirmed yet
Built & runningabout 14 miles awaySkybox Austin data center campus (Pflugerville)
Pflugerville, Travis County
π Nov 2023: State filing for Skybox Austin 2 in Pflugerville; construction set for Dec. 2023 to Oct.β¦
Reported in the news, not confirmed yet
What you can do
- Get told first.
We'll email you if anything changes in Coupland City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Depending on where you live in Coupland City: Oncor Electric Delivery Company LLC (company) or City of Bartlett (not available) or Pedernales Electric Co-op, Inc. (co-op (owned by its members)) or Bluebonnet Electric Co-op, Inc. (co-op (owned by its members)) or Bartlett Electric Co-op, Inc. (co-op (owned by its members)).
In much of Texas you can pick who sells you power, but this company owns the power lines.