πŸ§ͺ Preview: Pennsylvania test version. Other states are being added.
πŸ“£ Report Something
USA β€Ί Texas β€Ί Hood County β€Ί Cresson City

No project in Cresson City, but 6 nearby

Who decides here: the City Council of Cresson City votes on zoning. The Hood County may review big projects too.

Nearby (within 15 miles)

Approved, not built yetabout 13 miles away

Sailfish 'Comanche Circle' data center campus (near Tolar)

Unincorporated Hood County, Hood County

2,100 acres

πŸ•’ June 9, 2026: Commissioners Court approved the concept plan without conditions, 3-1.

Stopped or cancelledabout 13 miles away

'Fort Spunky' data center (Pacifico Energy, Hood County)

Unincorporated Hood County, Hood County

862 acres

πŸ•’ 2026: Pacifico Energy sued Hood County, saying it lacked power to deny the project over water.

Reported in the news, not confirmed yet

Built & runningabout 13 miles away

MARA (Marathon) bitcoin mining data center (Granbury area)

Unincorporated Hood County, Hood County

for Marathon (bitcoin mining)

πŸ•’ 2023: Marathon Digital bought the Granbury site from Generate Capital for $178.6 million.

Reported in the news, not confirmed yet

Status unclearabout 13 miles away

'Project Red' and 'Project Yellow' data centers (Hood County)

Unincorporated Hood County, Hood County

677 acres

πŸ•’ July 21, 2026: District Judge Bryan Bufkin dismissed the developers' lawsuit with prejudice.

Status unclearabout 13 miles away

Amazon 'Project Spectrum' data center campus (Coates Road, near Comanche Peak)

Unincorporated Hood County, Hood County

1,265 acres Β· for Amazon Web Services

πŸ•’ May 26, 2026: Hood County Commissioners Court accepted the conditional plan, 3-0 (two commissioners ab…

Reported in the news, not confirmed yet

Approved, not built yetabout 15 miles away

Bilateral Energy 'Project Patriot' power plant and data center campus (Knox Ranch, Granbury)

Granbury, Hood County

2,000 acres

πŸ•’ July 13, 2026: Residents filed petitions to recall the mayor and most council members.

Built & runningBeing builtApproved, not built yetProposedStopped or cancelled

What you can do

  1. Get told first.
    We'll email you if anything changes in Cresson City.
  2. Go to council meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
πŸ“£ Report something here

πŸ”” Get told first

We'll email you when something changes in Cresson City. Nothing else.

⚑ Your electric company

Depending on where you live in Cresson City: Oncor Electric Delivery Company LLC (company) or Texas-new Mexico Power Co. (company) or United Electric Co-op Service Inc. (co-op (owned by its members)) or Tri-county Electric Co-op, Inc. (co-op (owned by its members)).

In much of Texas you can pick who sells you power, but this company owns the power lines.