No project in Double Oak Town, but 5 nearby
Who decides here: the Town Council of Double Oak Town votes on zoning. The Denton County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Circle T data center (Westlake, near Keller)
Westlake, Tarrant County
90 acres
🕒 Sept 25, 2026: A Tarrant County district judge ended the temporary order that had blocked the Westlake …
Being builtabout 11 miles awayQTS Fort Worth campus expansion (FTW1, 14100 Park Vista Blvd.)
Fort Worth, Tarrant County
53 acres
🕒 2026: QTS filed a $300 million, 147,946 sq ft addition (FTW1 DC1 Expansion), July 2026 to Oct.…
Reported in the news, not confirmed yet
Approved, not built yetabout 12 miles awayQumulusAI modular data center (Denton)
Denton, Denton County
4 acres
🕒 Jan 13, 2026: City Council approved the permit and a tax break for 8 prefab data center 'pods' on 4 ac…
Reported in the news, not confirmed yet
Proposedabout 12 miles awayColovore Alliance AI data center (AllianceTexas)
Fort Worth, Denton County
🕒 Sept 30, 2026: Colovore filed plans for a $430 million, 156,500 sq ft liquid-cooled data center.
Reported in the news, not confirmed yet
Being builtabout 12 miles awayCore Scientific / CoreWeave AI data center (Jim Christal Road, Denton)
Denton, Denton County
78.85 acres · for CoreWeave (planned user, per 2024 reports)
🕒 Nov 19, 2024: City Council voted to lease 78.85 acres of city land and approve a new power deal for th…
What you can do
- Get told first.
We'll email you if anything changes in Double Oak Town. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Double Oak Town: Oncor Electric Delivery Company LLC (company) or Texas-new Mexico Power Co. (company) or Wise Electric Co-op Inc. (co-op (owned by its members)) or Tri-county Electric Co-op, Inc. (co-op (owned by its members)) or Denton County Electric Co-op, Inc. (co-op (owned by its members)) or Cooke County Electric Co-op Assn (co-op (owned by its members)).
In much of Texas you can pick who sells you power, but this company owns the power lines.
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Texas.