No project in Corral City Town, but 5 nearby
Who decides here: the Town Council of Corral City Town votes on zoning. The Denton County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Colovore Alliance AI data center (AllianceTexas)
Fort Worth, Denton County
🕒 Sept 30, 2026: Colovore filed plans for a $430 million, 156,500 sq ft liquid-cooled data center.
Reported in the news, not confirmed yet
Being builtabout 8 miles awayQTS Fort Worth campus expansion (FTW1, 14100 Park Vista Blvd.)
Fort Worth, Tarrant County
53 acres
🕒 2026: QTS filed a $300 million, 147,946 sq ft addition (FTW1 DC1 Expansion), July 2026 to Oct.…
Reported in the news, not confirmed yet
Status unclearabout 8 miles awayCircle T data center (Westlake, near Keller)
Westlake, Tarrant County
90 acres
🕒 Sept 25, 2026: A Tarrant County district judge ended the temporary order that had blocked the Westlake …
Being builtabout 9 miles awayCore Scientific / CoreWeave AI data center (Jim Christal Road, Denton)
Denton, Denton County
78.85 acres · for CoreWeave (planned user, per 2024 reports)
🕒 Nov 19, 2024: City Council voted to lease 78.85 acres of city land and approve a new power deal for th…
Approved, not built yetabout 9 miles awayQumulusAI modular data center (Denton)
Denton, Denton County
4 acres
🕒 Jan 13, 2026: City Council approved the permit and a tax break for 8 prefab data center 'pods' on 4 ac…
Reported in the news, not confirmed yet
What you can do
- Get told first.
We'll email you if anything changes in Corral City Town. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Corral City Town: Oncor Electric Delivery Company LLC (company) or Texas-new Mexico Power Co. (company) or Wise Electric Co-op Inc. (co-op (owned by its members)) or Tri-county Electric Co-op, Inc. (co-op (owned by its members)) or Denton County Electric Co-op, Inc. (co-op (owned by its members)) or Cooke County Electric Co-op Assn (co-op (owned by its members)).
In much of Texas you can pick who sells you power, but this company owns the power lines.
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Texas.