No project in Grapevine City, but 6 nearby
Who decides here: the City Council of Grapevine City votes on zoning. The Dallas County may review big projects too.
Nearby (within 15 miles)
Microsoft data centers (four buildings, Irving)
Irving, Dallas County
for Microsoft
π Dec 12, 2024: Irving City Council approved tax breaks for four Microsoft data centers.
Approved, not built yetabout 9 miles awayQTS Irving campus expansion (three buildings)
Irving, Dallas County
π Dec 12, 2024: Irving City Council approved tax breaks for three QTS data centers.
Being builtabout 9 miles awayPowerHouse Irving data center campus (111 Customer Way)
Irving, Dallas County
50 acres
Reported in the news, not confirmed yet
Approved, not built yetabout 9 miles awayKDC data center on University of Dallas land (Irving)
Irving, Dallas County
π July 2024: Irving City Council approved rezoning for the data center.
Reported in the news, not confirmed yet
Status unclearabout 10 miles awayCircle T data center (Westlake, near Keller)
Westlake, Tarrant County
90 acres
π Aug 18, 2026: Keller City Council voted to take legal action against Westlake over the project.
Proposedabout 14 miles awayProvident data center (old Santander site, Rufe Snow Drive)
North Richland Hills, Tarrant County
π June 23, 2026: Hundreds of residents attended Provident's information meeting and questioned the develoβ¦
Reported in the news, not confirmed yet
What you can do
- Get told first.
We'll email you if anything changes in Grapevine City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Depending on where you live in Grapevine City: Oncor Electric Delivery Company LLC (company) or Texas-new Mexico Power Co. (company) or Trinity Valley Electric Co-op Inc. (co-op (owned by its members)) or Farmers Electric Co-op, Inc. (co-op (owned by its members)) or Hilco Electric Cooperative, Inc. (co-op (owned by its members)).
In much of Texas you can pick who sells you power, but this company owns the power lines.
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Texas.