No project in Harlingen City, but 3 nearby
Who decides here: the City Council of Harlingen City votes on zoning. The Cameron County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
FluidStack data center (outside Harlingen)
Unincorporated Cameron County, Cameron County
1,100 acres
🕒 Sept 10, 2026: FluidStack announced a $4 billion first phase on more than 1,100 acres; Cameron County i…
Reported in the news, not confirmed yet
Proposedabout 14 miles awaySoluna 'Project Ellen' crypto and AI data center (South Texas wind farm)
Unincorporated Cameron County, Cameron County
🕒 April 17, 2025: Soluna announced a power term sheet for Project Ellen.
Reported in the news, not confirmed yet
Built & runningabout 15 miles awaySoluna 'Project Kati' bitcoin and AI data center (Willacy County)
Unincorporated Willacy County, Willacy County
for Bitcoin mining and AI customers
🕒 Oct 7, 2026: Soluna KK Energy Service Co LLC registered 'Project Kati II' with the Texas Department o…
Reported in the news, not confirmed yet
Local votes and rules
⏸️ Pause on new data centers
Harlingen City Commission approved a 120-day pause on data centers in May 2026 while it studies water, sewer and power systems and updates city rules. The pause also covers land that asks to join the city. It was set to end in mid-October; in August the city gave first approval to a 60-day extension through December.
What you can do
- Get told first.
We'll email you if anything changes in Harlingen City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Harlingen City: Magic Valley Electric Co-op Inc. (co-op (owned by its members)) or AEP Texas Central Company (company).
In much of Texas you can pick who sells you power, but this company owns the power lines.
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Texas.