Soluna 'Project Kati' bitcoin and AI data center (Willacy County)
Also called: Kati 1, Kati 2
Soluna runs an 83-megawatt data center called Kati 1 in Willacy County, next to a wind farm, mostly for bitcoin mining. It plans a second phase for AI, bringing the campus to 166 megawatts. The state grid operator has given the full campus a conditional OK.
What happens next?
Where things stand: Built & running Kati 1 (83 MW) running. On Oct. 7, 2026 Soluna filed state plans for Kati 2, a 112 MW AI data center building planned for Oct. 2026 to Oct. 2027.
❓ 3 open questions about it: see below.
📣 Report noise, water or power bill changes
Last checked Oct 19, 2026.
🕒 Latest update (Oct 7, 2026): Soluna KK Energy Service Co LLC registered 'Project Kati II' with the Texas Department of Licensing and Regulation: one AI data center building of about 471,884 sq ft with about 112 MW of computer load, estimated at $471.8 million, at 1392 FM 1420 in the Santa Monica area. Planned dates: Oct. 8, 2026 to Oct. 8, 2027.
What we know
- 📍 WhereUnincorporated Willacy County, Willacy County
- 🏢 CompanySoluna Holdings
- 👤 Built forBitcoin mining and AI customers
- ⚡ Power it needs166 megawatts (about as much as 132,800 homes)
- 🔌 Where the power comes fromNext to a wind farm (Las Majadas wind farm, per tracker) and the ERCOT grid
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How loud is the site for neighbors? 🙋 I'll find out ·
- How much water does it use? 🙋 I'll find out ·
- Has construction of Kati 2 started? 🙋 I'll find out ·
What happened so far
- Sept 8, 2026Soluna energized the last 14 MW of Kati 1 and got conditional ERCOT approval for all 166 MW.
- Oct 7, 2026Soluna KK Energy Service Co LLC registered 'Project Kati II' with the Texas Department of Licensing and Regulation: one AI data center building of about 471,884 sq ft with about 112 MW of computer load, estimated at $471.8 million, at 1392 FM 1420 in the Santa Monica area. Planned dates: Oct. 8, 2026 to Oct. 8, 2027.
Drag the slider to compare the land before and now.
Where this comes from
- Soluna Finishes Kati 1 and Secures Conditional Base Load Position for All 166 MW in ERCOT · Business Wire (Soluna) via Nasdaq · Sept 8, 2026
- Texas data centers map and list · Cleanview (tracker) · Oct 2026
- TDLR TABS TABS2027003019: Project Kati II (MFE-A-Kati2 - Building 1), Soluna KK Energy Service Co LLC, 1392 FM 1420 · Texas Department of Licensing and Regulation · Oct 7, 2026