Besides Project Temple, Rowan Digital Infrastructure has two more data center projects in Temple: Project Stampede (2 buildings, about 270 acres) and Project Ranger (1 building). The City Council approved a development deal and annexation for Stampede in April 2026 after an almost 8-hour meeting. Residents then started a recall effort against the mayor and council members.
Where things stand: Stampede's development deal was approved in April 2026; Rowan says 5 of its 6 Temple buildings are approved and 4 are being built.
🕒 Latest update (May 7, 2026): Council approved annexation, zoning and utility items for a three-phase Rowan data center project in Synergy Park.
What we know
- 📍 WhereSynergy Park area, south Temple, Temple, Bell County
- 🏢 CompanyRowan Digital Infrastructure
- 💧 WaterCity of Temple
- ❄️ CoolingClosed-loop cooling that does not need a steady water supply beyond staff use (company statement)
- 💵 Cost$2.1 billion
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How many megawatts will Stampede and Ranger use? 🙋 I'll find out
- Who is the tenant? 🙋 I'll find out
- What tax breaks were given for Stampede and Ranger? 🙋 I'll find out
- Is Project Ranger under construction yet? 🙋 I'll find out
What happened so far
- April 16, 2026City Council voted 4-0 for a development agreement with Rowan and to annex land for the city's third data center.
- May 7, 2026Council approved annexation, zoning and utility items for a three-phase Rowan data center project in Synergy Park.
Local votes and rules
✅ Approved
Rowan Digital Infrastructure asked Temple to approve the 'Lasso' building, the last of six data centers on its Temple campus, on a new site after Rowan gave land to the city for a landfill expansion. The Planning and Zoning Commission heard it on August 17, 2026, with City Council to follow in September. The city is also weighing a tax break, annexation and new rules with a 200-foot buffer between data centers and homes.
Drag the slider to compare the land before and now.
Where this comes from
- Temple council reaches development agreement for city's third data center · KXXV · April 17, 2026
- Rowan Digital Infrastructure seeks approval for 6th and final data center in Temple · KWTX · Aug 12, 2026
- Rowan Digital Infrastructure pursues final planned data center in Temple amid community opposition · KXXV · Aug 9, 2026
- $4bn+ Rowan Temple Data Center Campus Advances Despite Water and Power Questions · Construction Review Online · Sept 14, 2026
- City of Temple City Council meeting summary (Rowan annexation, zoning and utility items) · Govly (meeting summary) · May 7, 2026
See something wrong? Tell us and we'll fix it.