Rowan 'Project Temple' data center campus, incl. Lasso building (Temple)
Also called: Project Lasso, Lasso building, Rowan Temple AUS01/AUS02
Rowan Digital Infrastructure is building a 3-building data center campus in Temple's Synergy industrial park, about 300 megawatts in all. The city annexed and zoned the land in fall 2025. The third building, called 'Lasso', moved to a new parcel because the city needs the original spot for its landfill, so it needs a new approval and tax break.
Where things stand: Two buildings under construction. Third building ('Lasso') was set for a final City Council vote on Sept. 17, 2026; result not yet confirmed.
🕒 Latest update (Sept 3, 2026): City Council held a first hearing on annexing land and a tax break for Lasso; residents spoke for and against.
What we know
- 📍 WhereSynergy Southeast Industrial Park, south Temple, Temple, Bell County
- 🏢 CompanyRowan Digital Infrastructure
- ⚡ Power it needs300 megawatts (about as much as 240,000 homes)
- 🔌 Where the power comes fromGrid power (Oncor/ERCOT area). Rowan says it will 'pay its own way' on power.
- 💧 WaterCity of Temple
- ❄️ CoolingAir-chilled closed-loop system; 1 to 2 million gallons to fill each building, then about 4,000 gallons a day per building for staff use (city estimate)
- 💵 Cost$2.1 billion
- 💸 Tax breaksResidents say the city gave Rowan a 50% property tax break. Rowan agreed to pay about $32 million (about 45%) of a $71.1 million south Temple water project and for an aquifer storage well.
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Did the City Council approve the Lasso building on Sept. 17, 2026? 🙋 I'll find out
- How many megawatts will each building use, and who is the tenant? 🙋 I'll find out
- How many diesel backup generators are planned? 🙋 I'll find out
- Will new high-voltage power lines be built? 🙋 I'll find out
What happened so far
- Sept 2025Temple Planning and Zoning and City Council began approving Project Temple (annexation, zoning, development deals, tax breaks).
- Jan 2026Rowan broke ground on the $700 million first phase at 1707 and 2351 Bob White Road; operations expected in 2027 with power from Oncor.
- Aug 17, 2026Planning and Zoning Commission hearing on the Lasso building.
- Sept 3, 2026City Council held a first hearing on annexing land and a tax break for Lasso; residents spoke for and against.
Local votes and rules
✅ Approved
Rowan Digital Infrastructure asked Temple to approve the 'Lasso' building, the last of six data centers on its Temple campus, on a new site after Rowan gave land to the city for a landfill expansion. The Planning and Zoning Commission heard it on August 17, 2026, with City Council to follow in September. The city is also weighing a tax break, annexation and new rules with a 200-foot buffer between data centers and homes.
Drag the slider to compare the land before and now.
Where this comes from
- Rowan Digital Infrastructure seeks approval for 6th and final data center in Temple · KWTX · Aug 12, 2026
- Rowan Digital Infrastructure pursues final planned data center in Temple amid community opposition · KXXV · Aug 9, 2026
- Temple council talks data center tax breaks and regulations amid resident transparency concerns · KXXV · Sept 4, 2026
- $4bn+ Rowan Temple Data Center Campus Advances Despite Water and Power Questions · Construction Review Online · Sept 14, 2026
- Rowan starts work on 300MW data center in Temple, Texas · DatacenterDynamics · Jan 6, 2026
- City of Temple City Council meeting summary (Rowan annexation, zoning and utility items) · Govly (meeting summary) · May 7, 2026