No project in Factoryville Borough, but 17 nearby
Who decides here: the Borough Council of Factoryville Borough votes on zoning. The Wyoming County Planning Commission usually reviews big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Popca LLC data center campus (Newton Township)
Newton Township, Lackawanna County
76 acres
🕒 Sept 18, 2026: The Times-Tribune listed the Newton project (2 buildings, 76 acres) as denied by the tow…
Proposedabout 9 miles awayScranton Materials data center campus (Ransom Township)
Ransom Township, Lackawanna County
251 acres
🕒 Sept 3, 2026: News reports said the developer's second lawsuit (asking a judge to rule on the zoning) …
Proposedabout 10 miles awayDickson City Development data center (Bell Mountain)
Dickson City, Lackawanna County
🕒 Sept 18, 2026: The Times-Tribune listed the Bell Mountain project (4 buildings) as denied by the zoning…
Stopped or cancelledabout 11 miles awayBlakely data center campus
Blakely, Lackawanna County
209 acres
🕒 Sept 12, 2025: Developers withdrew the zoning change request after the borough declined another public …
Stopped or cancelledabout 11 miles awayWildcat Ridge data center campus (Archbald)
Archbald, Lackawanna County
574 acres
🕒 Oct 30, 2026: A lawyer for the developer, Cornell Realty Management, sent a legal notice to a county c…
Stopped or cancelledabout 11 miles awayMudiita data center campus idea (Ransom Township)
Ransom Township, Lackawanna County
530 acres
🕒 July 27, 2026: Owner said he does not plan a data center there right now; websites advertising an all-e…
Proposedabout 12 miles awayProject Gravity (Archbald)
Archbald, Lackawanna County
186 acres · for A future hyperscale tenant (not named)
🕒 Oct 2026: Corscale held an open house at the borough building. It said the campus would be 475 meg…
Local votes and rules
📜 Data center rules · Wyoming County
Wyoming County planners reviewed a draft change to the county land development rules aimed at data centers. They voted unanimously to recommend calling it 'High-Intensity Nonresidential Land Development' instead of naming data centers, so the rules cover other big projects too. The commissioners have not adopted it yet.
What you can do
- Get told first.
We'll email you if anything changes in Factoryville Borough. - Go to borough meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Factoryville Borough: PPL Electric Utilities Corp. (company) or Claverack Rural Electric Co-op Inc. (co-op (owned by its members)).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.