No project in Delano Township, but 9 nearby
Who decides here: the Township Supervisors (in some larger townships, the Board of Commissioners) of Delano Township votes on zoning. The Schuylkill County Planning Commission usually reviews big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Amazon (AWS) Kline Township campus
Kline Township, Schuylkill County
346 acres · for Amazon
🕒 Sept 30, 2026: At a special meeting, township supervisors voted unanimously to approve Amazon's data ce…
Proposedabout 7 miles awayProject Hazelnut (NorthPoint, Hazle Township)
Hazle Township, Luzerne County
1,280 acres · for Amazon Web Services (reported)
🕒 Nov 9, 2026: Residents packed a township meeting at Hazleton Area High School on the revised data cen…
Stopped or cancelledabout 8 miles awayWest Hazleton data center site (behind Valmont Shopping Plaza)
West Hazleton, Luzerne County
🕒 Dec 2025: Reported as withdrawn.
Reported in the news, not confirmed yet
Status unclearabout 8 miles awaySugarloaf Township data center (Tomhicken Road)
Sugarloaf Township, Luzerne County
185 acres
🕒 Sept 18, 2026: The Times-Tribune listed the LBT Sugarloaf project (6 buildings, 185 acres) as seeking a…
Reported in the news, not confirmed yet
Proposedabout 8 miles awayNorthPoint data center on Tresckow Mountain (Banks and Packer townships)
Banks Township, Carbon County
1,200 acres
🕒 Sept 30, 2025: NorthPoint met the public in Tresckow. About 150 people came; many said they do not want…
Proposedabout 9 miles awayKeel Infrastructure Panther Creek / Carbon Node East data center (Nesquehoning)
Nesquehoning, Carbon County
336 acres
🕒 Aug 21, 2026: Keel said the closed-loop cooling system would need about 700,000 gallons to fill at the…
What you can do
- Get told first.
We'll email you if anything changes in Delano Township. - Go to township meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
PPL Electric Utilities Corp. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.