Proposed

NorthPoint data center on Tresckow Mountain (Banks and Packer townships)

Also called: Spring Mountain Quakake Tunnel (NorthPoint Development), Tresckow data center

NorthPoint Development, the same company behind Project Hazelnut, bought about 1,200 acres on Tresckow Mountain in Banks and Packer townships for a possible data center. If it does not use a closed cooling system, it could draw up to 2 million gallons a day from the Quakake mine tunnel. Neighbors have spoken against it.

โœ” ConfirmedSourceLast checked: Oct 6, 2026

Where things stand: NorthPoint held public sessions in fall 2025 and said it would seek a zoning overlay. DEP lists it as proposed with no permit applications received.

๐Ÿ•’ Latest update (Sept 30, 2025): NorthPoint met the public in Tresckow. About 150 people came; many said they do not want it. A second session was planned in Packer Township.

What we know

  • ๐Ÿ“ WhereAbout 1,200 acres on top of Tresckow Mountain, crossing into Packer Township, Banks Township, Carbon County
  • ๐Ÿข CompanyNorthPoint Development (Kansas City, Missouri)
  • ๐ŸŒณ Size1,200 acres
  • ๐Ÿ”Œ Where the power comes fromAn existing power line crosses the land; the developer said that is why it chose the site.
  • ๐Ÿ’ง WaterPossibly water from the Quakake Tunnel (old mine water), cleaned and returned
  • โ„๏ธ CoolingNot decided. The developer said a closed system would use less water.

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Sept 30, 2025
    NorthPoint met the public in Tresckow. About 150 people came; many said they do not want it. A second session was planned in Packer Township.
๐Ÿ›ฐ๏ธ See it from above

Drag the slider to compare the land before and now.

2018โ€“20202021โ€“2023
Photos: PEMA / PASDA, Pennsylvania aerial photos.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Data center developer presents plan in Tresckow ยท Times News ยท Oct 1, 2025
  2. PA Data Center Permit Tracker - all projects list (CSV behind the DEP map) ยท Pennsylvania Department of Environmental Protection ยท Oct 6, 2026

See something wrong? Tell us and we'll fix it.