2 data center projects in Bethlehem City
Who decides here: the City Council of Bethlehem City votes on zoning. The Northampton County Planning Commission usually reviews big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
In Bethlehem City
Industrial Drive data center (2184 Industrial Drive, Bethlehem)
Bethlehem, Northampton County
7 acres
🕒 Nov 12, 2026: The Bethlehem Planning Commission voted 5-0 to approve the site plan for the two-story, …
ProposedCommerce Center Boulevard data center (Bethlehem)
Bethlehem, Northampton County
🕒 Oct 20, 2026: Bethlehem City Council passed new data center rules 6-1. Because this plan was filed bef…
Reported in the news, not confirmed yet
Nearby (within 15 miles)
J.G. Petrucci data center (1024 N. Bradford St., Allentown)
Allentown, Lehigh County
🕒 Sept 23, 2026: Regional planners said the plan is missing cooling, water, power and noise details.
Proposedabout 8 miles awayQuantm Group data center (2401 W. Emaus Ave., Allentown)
Allentown, Lehigh County
14 acres
🕒 Sept 2026: The Lehigh County Authority, which runs Allentown's public water, said a data center wil…
Approved, not built yetabout 9 miles awayPrologis Lehigh Valley East 16 warehouse-to-data-center (Allen Township)
Allen Township, Northampton County
🕒 April 21, 2026: The Lehigh Valley Planning Commission said it could not fully review the plan and asked …
Proposedabout 10 miles awayProject Atlas (Edged, South Whitehall Township)
South Whitehall Township, Lehigh County
410 acres
🕒 Sept 23, 2026: At a special planning commission session at Parkland High School, the developer said it …
Stopped or cancelledabout 14 miles awayAir Products Cetronia Road data center (Upper Macungie Township)
Upper Macungie Township, Lehigh County
194 acres
🕒 Aug 11, 2026: Air Products dropped the project.
Local votes and rules
✅ Approved
The Bethlehem Planning Commission voted 5-0 to approve the site plan for a two-story data center at 2184 Industrial Drive along Route 22, plus three exceptions. About 30 people spoke against it. The plan was filed before the city banned data centers in this district, so the new rules do not apply.
📜 Data center rules
Bethlehem City Council voted 6-1 to pass the city's first data center zoning rules. Data centers must be at least 1,000 feet from homes, schools, day cares, parks and hospitals, and are banned in the Planned Industrial district. Two plans filed earlier (Industrial Drive and Commerce Center Boulevard) are reviewed under the old rules.
What you can do
- Get told first.
We'll email you if anything changes in Bethlehem City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
PPL Electric Utilities Corp. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.
🙋 Open tasks here
- Who is the developer and end user?
- How much air pollution from on-site gas generation?
- Who would use the Industrial Drive data center (the end user)?
- When will the state approve the sewer plans and stormwater permit for the Industrial Drive data center?
- How much water will the on-site gas turbines use each year?
- How much power and water would the Commerce Center Boulevard data center use?
- Who would use the data center (the end user)?
- When will the Bethlehem Planning Commission review the plan?
- Would it have backup diesel generators or its own power plant?