J.G. Petrucci data center (1024 N. Bradford St., Allentown)
A 146,000-square-foot, roughly 100-megawatt data center is proposed on North Bradford Street in Allentown. Regional planners said the city should not approve it without key information on water, power and noise.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the City Council of Allentown City.
Where things stand: Proposed Lehigh Valley Planning Commission said in Sept. 2026 the plan lacks key details; city approval still needed.
❓ 4 open questions about it: see below.
Last checked Oct 7, 2026.
🕒 Latest update (Sept 23, 2026): Regional planners said the plan is missing cooling, water, power and noise details.
What we know
- 📍 Where1024 N. Bradford St., near the IronPigs stadium and a charter school, Allentown, Lehigh County
- 🏢 CompanyJ.G. Petrucci Company
- ⚡ Power it needs100 megawatts (about as much as 80,000 homes)
- 🔌 Where the power comes fromDeveloper says it would pay its own way for power (PPL)
- 💧 WaterLehigh County Authority (Allentown public water), if the authority agrees to serve it
- ❄️ CoolingClosed-loop cooling (developer claim)
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How many backup generators? 🙋 I'll find out ·
- How much water will it use? 🙋 I'll find out ·
- When will the city vote? 🙋 I'll find out ·
- Has the Lehigh County Authority given this data center a will-serve letter, and for how many gallons a day? 🙋 I'll find out ·
🔎 What we checked
- Oct 6, 2026: We checked the Delaware River Basin Commission's (DRBC) list of pending applications (August 2026): there is no application for this data center. DRBC said in November 2025 it had not received any data center applications. A data center needs its own DRBC approval only if it takes more than 100,000 gallons a day from its own wells or streams, or discharges more than 50,000 gallons a day (lower limits in some protected areas). Buying water from a water company does not need a separate DRBC approval.
What happened so far
- Aug 2026J.G. Petrucci filed plans for a 100 megawatt, 146,000-square-foot data center with its own substation. It said building could start in early 2027.
- Sept 2026The Lehigh County Authority, which runs Allentown's public water, said a data center will not come to Allentown unless the authority can supply the water. It said its system moves about 26 million gallons a day, about half of its 1960s-70s level, and that some existing businesses already use 1 to 2 million gallons a day, more than a proposed data center would. The authority was in a drought warning at the time.
- Sept 23, 2026Regional planners said the plan is missing cooling, water, power and noise details.
Local votes and rules
📜 Data center rules
Allentown City Council introduced a bill that would allow data centers only in industrial zones.
Drag the slider to compare the land before and now.
Where this comes from
- What the latest planning reviews say about data center proposals in Allentown, Bethlehem · lehighvalleylive.com (via Yahoo News) · Sept 23, 2026
- Revised plans for Allentown data center to be scrutinized; what's changed? · WFMZ-TV 69 News · Sept 2026
- 100MW data center proposed in Allentown, Pennsylvania · DatacenterDynamics · Aug 20, 2026
- Data centers coming to Allentown? LCA says there's plenty of water — but it's not infinite · WFMZ-TV 69 News · Sept 2026
- Frequently Asked Questions: Data Centers · Delaware River Basin Commission · Nov 24, 2025
- DRBC Project Review: Pending Project Status (August 2026) · Delaware River Basin Commission · Aug 2026
- OpenStreetMap map check · OpenStreetMap contributors · Oct 7, 2026