Project Atlas (Edged, South Whitehall Township)
Also called: CDE Acquisitions LLC, Edged US
Edged wants to build three large data center buildings (725 megawatts) on 410 acres of farmland next to Parkland High School. It cut the plan from six buildings after strong opposition. A residents' group says it will fight it in court if needed.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Township Supervisors (in some larger townships, the Board of Commissioners) of South Whitehall Township.
Where things stand: Proposed Scaled-down plan (3 data center buildings, about 1.5 million sq ft on 410 acres). The planning commission took no decision on Sept. 23, 2026; the deadline for a decision was extended to Dec. 31, 2026. The developer said it will come back with a revised plan.
❓ 4 open questions about it: see below.
Last checked Oct 19, 2026.
🕒 Latest update (Sept 23, 2026): At a special planning commission session at Parkland High School, the developer said it was not asking for approval and would return with a revised plan. The decision deadline moved from Oct. 31 to Dec. 31, 2026.
What we know
- 📍 WhereAbout 410 acres at 2493 N. Cedar Crest Blvd., across from Parkland High School, South Whitehall Township, Lehigh County
- 🏢 CompanyEdged US (CDE Acquisitions LLC)
- 🏛️ Owned byEndeavour
- 🌳 Size410 acres
- ⚡ Power it needs725 megawatts (about as much as 580,000 homes)
- 🔌 Where the power comes fromDeveloper says it will pay for all power and grid upgrades
- ❄️ CoolingClosed-loop cooling; developer says no water from the township system
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- When will the planning commission and supervisors vote? 🙋 I'll find out ·
- Who is the end user? 🙋 I'll find out ·
- Will new high-voltage lines be needed for 725 megawatts? 🙋 I'll find out ·
- When will the South Whitehall planning commission take up the revised Project Atlas plan? (Decision deadline: Dec. 31, 2026.) 🙋 I'll find out ·
🔎 What we checked
- Oct 6, 2026: We checked the Delaware River Basin Commission's (DRBC) list of pending applications (August 2026): there is no application for this data center. DRBC said in November 2025 it had not received any data center applications. A data center needs its own DRBC approval only if it takes more than 100,000 gallons a day from its own wells or streams, or discharges more than 50,000 gallons a day (lower limits in some protected areas). Buying water from a water company does not need a separate DRBC approval.
What happened so far
- Dec 2025First plan: six data centers, over 5 million square feet, up to $9 billion.
- July 9, 2026New three-building plan (about 1.5 million sq ft, 725 MW) presented; township engineer did not recommend approval; residents asked for a public hearing.
- Sept 23, 2026At a special planning commission session at Parkland High School, the developer said it was not asking for approval and would return with a revised plan. The decision deadline moved from Oct. 31 to Dec. 31, 2026.
Local votes and rules
📜 Data center rules
South Whitehall Township is working on rules for data centers. As of March 2026 the draft was still under review and not yet passed. A 5.1 million square foot data center is planned in the township.
Drag the slider to compare the land before and now.
Where this comes from
- Residents push for public hearing as South Whitehall takes new look at hyperscale data center · Lehigh Valley Public Media · July 14, 2026
- Edged eyes 725MW data center campus in Pennsylvania · DatacenterDynamics · 2026
- PA DEP Data Center Permit Tracker · Pennsylvania DEP · Oct 6, 2026
- South Whitehall Township home page - Events & Agendas (archived Oct. 5, 2026) · South Whitehall Township · Oct 6, 2026
- Frequently Asked Questions: Data Centers · Delaware River Basin Commission · Nov 24, 2025
- DRBC Project Review: Pending Project Status (August 2026) · Delaware River Basin Commission · Aug 2026
- Project Atlas meeting ends without decision; deadline for vote on plan pushed to New Year's Eve · WFMZ · Sept 23, 2026
See something wrong? Tell us and we'll fix it.