No project in Bridgeport Borough, but 6 nearby
Who decides here: the Borough Council of Bridgeport Borough votes on zoning. The Montgomery County Planning Commission usually reviews big projects too.
Nearby (within 15 miles)
Data center at former steel mill, 900 Conshohocken Road (Plymouth Township)
Plymouth Township, Montgomery County
🕒 Aug 6, 2026: Zoning Hearing Board hearing at Colonial Middle School ended without a decision; more se…
Proposedabout 2 miles awayMLP Ventures data centers (Upper Merion Township)
Upper Merion Township, Montgomery County
🕒 Sept 10, 2026: Supervisors voted to send the township lawyer to oppose the developer's variance request…
Proposedabout 13 miles awayProject Laurel (MCD 7 LLC, Limerick Township)
Limerick Township, Montgomery County
192 acres · for Not named (developer cites NDAs)
🕒 April 2026: Township planners asked for new will-serve letters from Pennsylvania American Water to s…
Proposedabout 13 miles awayPennhurst data center (East Vincent Township)
East Vincent Township, Chester County
125 acres
🕒 June 26, 2026: Penn Hurst Holdings DE LLC appealed the denial to the Chester County Court of Common Ple…
Being builtabout 14 miles awaySentinel / Green Fig data center at Foote Mineral Superfund site (East Whiteland)
East Whiteland Township, Chester County
100 acres
🕒 Aug 26, 2026: Second stop-work order until Aqua confirms enough water.
Proposedabout 14 miles awayPublicker site data center (1301 Main St., Linfield, Limerick Township)
Limerick Township, Montgomery County
191.46 acres
🕒 Sept 2026: Township agreed to the developer's request to delay hearings. The extension runs to Jan.…
Local votes and rules
📌 Other · Montgomery County
The Montgomery County Planning Commission helped write the joint Data Center Ordinance Guide with Chester County. It gives towns sample rules, such as a 1,000-foot buffer from homes, a 60-foot height limit and night noise limits.
What you can do
- Get told first.
We'll email you if anything changes in Bridgeport Borough. - Go to borough meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
PECO Energy Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.