Proposed

Data center at former steel mill, 900 Conshohocken Road (Plymouth Township)

Developer Brian O'Neill (MLP Ventures) wants to turn the closed Cleveland-Cliffs steel mill at 900 Conshohocken Road into a data center of about 2 million square feet. His first application was withdrawn in 2025, but he refiled in 2026 and zoning hearings are under way.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ Next meeting of the people who decide: Thursday, November 19, 2026 (time not announced)

Plymouth Township Zoning Hearing Board

📍 Plymouth Township building (the Oct. 15 session was also streamed online). Check the township website for the time.

Next session of the special exception hearing, as reported by 6abc. Public comment will start only after the evidence part of the hearing ends.

The board meets on this day, but we don't know yet if this project is on the agenda. Call the office to check before you go.

Source

Where things stand: Proposed First application was withdrawn in Nov. 2025, but the developer refiled in May 2026 and also filed a zoning validity challenge in July. Zoning Hearing Board hearings continued on Oct. 15, 2026; no decision yet.

❓ 3 open questions about it: see below.

Last checked Oct 26, 2026.

🕒 Latest update (Oct 15, 2026): At the zoning hearing board session, the developer and his lawyers testified about noise, lighting, water and power use, jobs and taxes. Opponents' lawyers said experts should address those topics; experts are expected at later sessions. No public comment was taken.

What we know

  • 📍 Where900 Conshohocken Road (former Cleveland-Cliffs steel mill site), Plymouth Township, Montgomery County
  • 🏢 CompanyMLP Ventures (Brian O'Neill)
  • 🌳 Size66 acres

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Could it be refiled? 🙋 I'll find out ·
  • Will the nearby county-owned quarry be sold to a data center developer? 🙋 I'll find out ·
  • When is the next Zoning Hearing Board session on 900 Conshohocken Road, and when will the board decide? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 10, 2026: We checked WHYY reports: the former Cleveland-Cliffs steel mill site is 66 acres; the plan reuses 10 existing buildings for about 2 million square feet.

    What happened so far

    • Nov 17, 2025
      First application withdrawn at the zoning board because the developer's sale agreement was not final.
    • May 2026
      Developer resubmitted plans for a data center using 10 existing buildings.
    • June 9, 2026
      Township council released a statement; zoning hearing board hearing set for June 25.
    • July 21, 2026
      The developer also filed a validity challenge to Plymouth Township's zoning.
    • Aug 6, 2026
      Zoning Hearing Board hearing at Colonial Middle School ended without a decision; more sessions planned.
    • Sept 14, 2026
      Montgomery County asked for party status in the zoning case because it owns the old Ivy Rock Quarry across the road.
    • Sept 17, 2026
      A Zoning Hearing Board session was canceled because the agenda was not posted online as the state open-meetings law requires.
    • Oct 15, 2026
      The Zoning Hearing Board hearing continued at the township building; the board was to decide on the county's request for party status.
    • Oct 15, 2026
      At the zoning hearing board session, the developer and his lawyers testified about noise, lighting, water and power use, jobs and taxes. Opponents' lawyers said experts should address those topics; experts are expected at later sessions. No public comment was taken.

    Local votes and rules

    ✅ Approved

    A developer is asking the Plymouth Township Zoning Hearing Board for a special exception to turn the closed Cleveland-Cliffs steel mill on Conshohocken Road into a 2 million-square-foot AI data center. An earlier request was withdrawn in November 2025 over a legal standing problem. Hearings on the new request began in summer 2026 with no decision yet.

    May 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    2018–20202021–2023
    Photos: PEMA / PASDA, Pennsylvania aerial photos.