No project in New Columbus Borough, but 10 nearby
Who decides here: the Borough Council of New Columbus Borough votes on zoning. The Luzerne County Planning Commission usually reviews big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Salem 4 data center site (Moores 109 LLC, Salem Township)
Salem Township, Luzerne County
185 acres
Reported in the news, not confirmed yet
Proposedabout 7 miles awaySalem 3 data center campus (4-3 Glennbrook Group)
Salem Township, Luzerne County
4,466 acres
🕒 Oct 27, 2026: After a public hearing, Salem Township supervisors voted to nearly triple the data cente…
Built & runningabout 9 miles awayAmazon (AWS) Salem Township campus next to Susquehanna nuclear plant
Salem Township, Luzerne County
1,600 acres · for Amazon
🕒 Aug 5, 2026: SRBC staff inspected the campus and found no water-rule violations.
Built & runningabout 9 miles awayNautilus Cryptomine (bitcoin mining at Susquehanna nuclear plant)
Salem Township, Luzerne County
for Bitcoin mining
🕒 Oct 2024: TeraWulf sold its 25% share of the Nautilus mine to a Talen Energy company for about $92…
Approved, not built yetabout 9 miles awayQTS data center campus (Salem 2), Salem Township
Salem Township, Luzerne County
1,700 acres
🕒 Aug 22, 2026: Developers said construction is planned to begin in late 2026.
Proposedabout 11 miles awayHunlock Creek power plant data center idea (Castleton Commodities, Hunlock Township)
Hunlock Township, Luzerne County
🕒 Oct 8, 2026: The Luzerne County Planning Commission sent the county's data center zoning rules, which…
Reported in the news, not confirmed yet
Local votes and rules
🗺️ Zoning change · Luzerne County
Luzerne County is writing data center rules for the 19 towns that use county zoning. Every data center would need a special exception from the county zoning hearing board. The planning commission recommended it in May 2026 and meets Oct. 8 to review new changes from the county law office. County Council must still vote.
🗺️ Zoning change · Luzerne County
The Luzerne County Planning Commission sent the county's data center zoning rules to County Council and recommended adoption. Every data center would need a special exception from the county zoning hearing board. County Council has not set a vote date.
What you can do
- Get told first.
We'll email you if anything changes in New Columbus Borough. - Go to borough meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
UGI Utilities, Inc. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.