Proposed

Hunlock Creek power plant data center idea (Castleton Commodities, Hunlock Township)

Also called: Hunlock Data Center (Castleton Commodities), Hunlock Creek Energy Center

The owner of the Hunlock Creek gas power plant said it is interested in building a small data center next to the plant. Hunlock Township uses Luzerne County's zoning, so it has to wait for the county's new data center rules. Shell has since agreed to buy the plant, so the plan may change.

πŸ‘₯ Reported, not confirmed yetSourceLast checked: Oct 2026

Where things stand: Interest only. The owner told Luzerne County it wants a small data center next to its gas power plant, but it must wait for new county zoning rules.

πŸ•’ Latest update (Sept 2026): News roundup reported that Shell Energy North America is buying the 169 MW Hunlock Creek gas plant.

πŸ—“οΈ Next meeting of the people who decide: Oct 8, 2026 Β· 2:00 PM
Luzerne County Planning Commission. We don't know yet if Hunlock Creek power plant data center idea (Castleton Commodities, Hunlock Township) is on the agenda. Call the office to check before you go.
Review of the county's proposed data center zoning rules, which would cover Hunlock Township.
πŸ“ Luzerne County Courthouse, River Street, Wilkes-Barre.

What we know

  • πŸ“ WhereNext to the Hunlock Creek Energy Center along Route 11, Hunlock Township, Luzerne County
  • 🏒 CompanyCastleton Commodities International LLC
  • πŸ”Œ Where the power comes fromNext to the 169 MW Hunlock Creek natural gas power plant (Shell later agreed to buy the plant).

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • April 9, 2026
    County planning director said Castleton wants to build a small data center by its Hunlock Creek plant once the county zoning amendment passes.
  • Sept 2026
    News roundup reported that Shell Energy North America is buying the 169 MW Hunlock Creek gas plant.

Local votes and rules

πŸ—ΊοΈ Zoning change

Luzerne County is writing data center rules for the 19 towns that use county zoning. Every data center would need a special exception from the county zoning hearing board. The planning commission recommended it in May 2026 and meets Oct. 8 to review new changes from the county law office. County Council must still vote.

Oct 8, 2026
πŸ›°οΈ See it from above

Drag the slider to compare the land before and now.

2018–20202021–2023
Photos: PEMA / PASDA, Pennsylvania aerial photos.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. Interest expressed in data center by Hunlock Twp. power plant Β· Citizens' Voice Β· April 9, 2026
  2. In Case You Missed It: A.I./Data Center Articles (lists Shell purchase of Hunlock Creek plant) Β· PA Environment Digest Β· Sept 12, 2026
  3. PA Data Center Permit Tracker - all projects list (CSV behind the DEP map) Β· Pennsylvania Department of Environmental Protection Β· Oct 6, 2026
  4. Luzerne County's proposed data center zoning ordinance amendment up for discussion Thursday Β· Times Leader Β· Oct 4, 2026

See something wrong? Tell us and we'll fix it.