Send us a tip
ProposedBig (AI-size): 185 acres

Salem 4 data center site (Moores 109 LLC, Salem Township)

Also called: Salem 4

A fourth data center site has been proposed in Salem Township, on about 185 acres, by a company called Moores 109 LLC. It still needs a zoning change before it can file plans. Salem Township already has the Amazon campus, the QTS campus and the proposed Salem 3 campus.

👥 Reported, not confirmed yetSourceLast checked: Nov 2026

What happens next?

🗓️ Next meeting of the people who decide: Tuesday, November 24, 2026, 6:00 PM Eastern Time (local time)

Salem Township Board of Supervisors meeting

📍 Workshop meeting. The 2026 schedule lists 38 Bomboy Lane, Berwick, but recent meetings were moved to Berwick Assembly of God. Check the township website for the place.

Workshop meeting from the township's 2026 schedule. No data center item is known to be on the agenda.

The board meets on this day, but we don't know yet if this project is on the agenda. Call the office to check before you go.

Source

Where things stand: Proposed Waiting for a zoning change. After that it would need a master plan, land development approval and permits.

❓ 5 open questions about it: see below.

Last checked Nov 16, 2026.

What we know

  • 📍 WhereSalem Township, Luzerne County
  • 🏢 CompanyMoores 109 LLC
  • 🌳 Size185 acres
  • 🔌 Where the power comes fromDeveloper points to a nearby PPL substation
  • 💧 WaterDeveloper asked Pennsylvania American Water whether it has enough capacity

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Where exactly in Salem Township is the 185-acre Salem 4 site? 🙋 I'll find out ·
  • Who is behind Moores 109 LLC, and who would use the data center? 🙋 I'll find out ·
  • How many buildings and megawatts are planned? 🙋 I'll find out ·
  • When will supervisors consider the zoning change? 🙋 I'll find out ·
  • Did the Oct. 27, 2026 overlay vote include the 185-acre Moores 109 (Salem 4) site? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    Local votes and rules

    🗺️ Zoning change

    After a public hearing, Salem Township supervisors voted to nearly triple the township's data center overlay zone to almost 5,000 acres. This clears the zoning for the planned Salem 3 data center campus. The meeting agenda listed Ordinances No. 3 and No. 4 of 2026.

    Oct 27, 2026

    🗺️ Zoning change

    After a court voided its earlier votes, the Salem Township Planning Commission voted a third time to recommend a larger data center overlay zone. The zone would help a third data center project move forward. Township supervisors make the final decision.

    Sept 2026

    🗺️ Zoning change

    Salem Township supervisors scheduled a vote to expand the township's data center overlay zone for the Salem 3 campus, a planned 39-building project on more than 4,000 acres with its own power plant. Residents went to court over meeting notice and limits on public comment.

    Aug 26, 2026

    ⚖️ Court case

    A Luzerne County judge ruled that the Salem Township Planning Commission broke the state open-meetings law when some people were locked out of a meeting on a data center zoning overlay. Eight residents without a lawyer brought the case. The ruling voided the commission's earlier vote on an overlay for a third data center project, called Salem 3.

    Aug 25, 2026

    ✅ Approved

    The Salem Township Planning Commission recommended conditional approval of a revised master plan for a QTS data center campus. The new plan cuts the project from 18 buildings to 12 but adds 100 acres. It also involves closing parts of three local roads. Supervisors had approved an earlier master plan.

    May 2026

    🤝 Agreement with the company

    Salem Township supervisors approved a Blackstone QTS data center campus planned for about 1,700 acres bought from 96 landowners. The township received a $9 million community benefit agreement to pay for emergency medical services, roads and other infrastructure, and town services.

    March 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    2018–20202021–2023
    We only know the town, so this shows the town center, not the exact site. Photos: PEMA / PASDA, Pennsylvania aerial photos.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. 22 regional data center projects and where they stand · The Times-Tribune / Citizens' Voice · Sept 18, 2026
    2. Salem Township home page (meetings list) · Salem Township · Oct 19, 2026
    3. Salem Township Meetings 2026 (schedule) · Salem Township · 2026
    4. Salem Township Board of Supervisors workshop/special meeting agenda, Oct. 27, 2026 · Salem Township · Oct 27, 2026

    See something wrong? Tell us and we'll fix it.