No project in North Whitehall Township, but 8 nearby
Who decides here: the Township Supervisors (in some larger townships, the Board of Commissioners) of North Whitehall Township votes on zoning. The Lehigh County Planning Commission usually reviews big projects too.
Nearby (within 15 miles)
Project Atlas (Edged, South Whitehall Township)
South Whitehall Township, Lehigh County
410 acres
π July 9, 2026: New three-building plan (about 1.5 million sq ft, 725 MW) presented; township engineer dβ¦
Approved, not built yetabout 5 miles awayPrologis Lehigh Valley East 16 warehouse-to-data-center (Allen Township)
Allen Township, Northampton County
π April 21, 2026: The Lehigh Valley Planning Commission said it could not fully review the plan and asked β¦
Proposedabout 8 miles awayJ.G. Petrucci data center (1024 N. Bradford St., Allentown)
Allentown, Lehigh County
π Sept 23, 2026: Regional planners said the plan is missing cooling, water, power and noise details.
Stopped or cancelledabout 8 miles awayAir Products Cetronia Road data center (Upper Macungie Township)
Upper Macungie Township, Lehigh County
194 acres
π Aug 11, 2026: Air Products dropped the project.
Proposedabout 9 miles awayQuantm Group data center (2401 W. Emaus Ave., Allentown)
Allentown, Lehigh County
14 acres
π Sept 2026: The Lehigh County Authority, which runs Allentown's public water, said a data center wilβ¦
Proposedabout 10 miles awayDTA Alliance data center campus (Lower Towamensing Township)
Lower Towamensing Township, Carbon County
700 acres
π Sept 10, 2026: About 20 people attended a planning commission meeting raising water, noise and propertyβ¦
Local votes and rules
π Data center rules
North Whitehall Township has passed rules for data centers, according to a March 2026 news report. The exact rules were not given in the report.
What you can do
- Get told first.
We'll email you if anything changes in North Whitehall Township. - Go to township meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
PPL Electric Utilities Corp. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.