DTA Alliance data center campus (Lower Towamensing Township)
Also called: Blue Shamrock Golf Course, Murphy's Meadow LLC
Quarry and golf course owners want to build 13 data center buildings on about 700 acres off Fireline Road. They filed a legal challenge to the township's zoning. The township's public hearing on that challenge is set for Dec. 17, 2026.
What happens next?
🗓️ Public hearing: Thursday, December 17, 2026, 7:00 PM Eastern Time (local time)
Public hearing on the landowners' zoning challenge (curative amendment) for the data center campus.
How: Come to the hearing at the Aquashicola Fire Company and speak during public comment, or write to the township before the hearing.
✔ ConfirmedSourceNot live: please check with the office first.
🗓️ No meeting or deadline known yet.
Where things stand: Proposed Landowners filed a zoning challenge Sept. 1, 2026. The township has set the hearing for Dec. 17, 2026 at 7 p.m. at the Aquashicola Fire Company.
❓ 4 open questions about it: see below.
Last checked Nov 9, 2026.
🕒 Latest update (Oct 2026): DTA Alliance LLC and Murphy's Meadow LLC (both owned by DT Allen Contracting) filed a curative amendment in Bowmanstown Borough, asking to allow data centers on about 55 acres near Ore and Ridge streets, with a 375,000-square-foot building for cooling equipment. The filing estimates the total project cost at about $4 billion.
What we know
- 📍 WhereOff Fireline Road at Blue Shamrock Golf Course and the Alliance Sand Quarry (415 Golf Road), Lower Towamensing Township, Carbon County
- 🏢 CompanyDTA Alliance LLC and Murphy's Meadow LLC
- 🏛️ Owned byDT Allen Contracting (NJ) owns Murphy's Meadow
- 🌳 Size700 acres
- 🔌 Where the power comes fromA possible power generation building on site
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How much power and water would it use? 🙋 I'll find out ·
- Would it have its own power plant? 🙋 I'll find out ·
- Who is the end user? 🙋 I'll find out ·
- Is the Bowmanstown site part of the same data center campus as the Lower Towamensing site, and how would they connect? 🙋 I'll find out ·
🔎 What we checked
- Oct 6, 2026: We checked the Delaware River Basin Commission's (DRBC) list of pending applications (August 2026): there is no application for this data center. DRBC said in November 2025 it had not received any data center applications. A data center needs its own DRBC approval only if it takes more than 100,000 gallons a day from its own wells or streams, or discharges more than 50,000 gallons a day (lower limits in some protected areas). Buying water from a water company does not need a separate DRBC approval.
What happened so far
- Sept 1, 2026Owners filed a curative amendment saying the township's zoning illegally leaves out data centers.
- Sept 1, 2026DTA Alliance LLC, which has agreements to buy seven parcels (about 700 acres) along Fireline Road and Dairy Road, filed a challenge to the township's zoning and a proposed change that would create a data center overlay district.
- Sept 10, 2026About 20 people attended a planning commission meeting raising water, noise and property value concerns.
- Oct 2026The township solicitor said the developer asked to continue the Oct. 27 hearing. A new date in the week of Dec. 14 is expected.
- Oct 2026DTA Alliance LLC and Murphy's Meadow LLC (both owned by DT Allen Contracting) filed a curative amendment in Bowmanstown Borough, asking to allow data centers on about 55 acres near Ore and Ridge streets, with a 375,000-square-foot building for cooling equipment. The filing estimates the total project cost at about $4 billion.
Drag the slider to compare the land before and now.
Where this comes from
- Meeting Thursday to discuss data center · Times News · Sept 30, 2026
- Substantive validity challenge and curative amendment - data center use (application letter dated Sept. 1, 2026) · Lower Towamensing Township · Sept 1, 2026
- Curative amendment maps · Lower Towamensing Township · Sept 1, 2026
- Frequently Asked Questions: Data Centers · Delaware River Basin Commission · Nov 24, 2025
- DRBC Project Review: Pending Project Status (August 2026) · Delaware River Basin Commission · Aug 2026
- U.S. Census Geocoder result for 415 Golf Road, Palmerton, PA · U.S. Census Bureau · Oct 7, 2026
- OpenStreetMap map check · OpenStreetMap contributors · Oct 7, 2026
- DTA plans center in Bowmanstown; 375,000 square foot building to be used for cooling equipment · Times News · Oct 10, 2026
- Stop the Lower Towamensing Data Center! · Save Carbon County (resident group) · Nov 2026
- Lower Towamensing Township home page (news: curative amendment hearing rescheduled) · Lower Towamensing Township · Nov 9, 2026
See something wrong? Tell us and we'll fix it.