No project in Emmaus Borough, but 9 nearby
Who decides here: the Borough Council of Emmaus Borough votes on zoning. The Lehigh County Planning Commission usually reviews big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Quantm Group data center (2401 W. Emaus Ave., Allentown)
Allentown, Lehigh County
14 acres
🕒 Sept 2026: The Lehigh County Authority, which runs Allentown's public water, said a data center wil…
Stopped or cancelledabout 5 miles awayAir Products Cetronia Road data center (Upper Macungie Township)
Upper Macungie Township, Lehigh County
194 acres
🕒 Aug 11, 2026: Air Products dropped the project.
Proposedabout 7 miles awayJ.G. Petrucci data center (1024 N. Bradford St., Allentown)
Allentown, Lehigh County
🕒 Sept 23, 2026: Regional planners said the plan is missing cooling, water, power and noise details.
Proposedabout 8 miles awayProject Atlas (Edged, South Whitehall Township)
South Whitehall Township, Lehigh County
410 acres
🕒 Sept 23, 2026: At a special planning commission session at Parkland High School, the developer said it …
Proposedabout 8 miles awayUndisclosed data center (Hanover Land Development site, Upper Hanover Township)
Upper Hanover Township, Montgomery County
37 acres
Reported in the news, not confirmed yet
Being builtabout 8 miles awayTierPoint TekPark data center expansion (Breinigsville, Upper Macungie Township)
Upper Macungie Township, Lehigh County
137 acres · for TierPoint customers (colocation)
🕒 Aug 2026: DEP asked for public comment on a stormwater permit for PPL's new Breinigsville-Tek Park…
Approved, not built yetabout 9 miles awayIndustrial Drive data center (2184 Industrial Drive, Bethlehem)
Bethlehem, Northampton County
7 acres
🕒 Nov 12, 2026: The Bethlehem Planning Commission voted 5-0 to approve the site plan for the two-story, …
Proposedabout 11 miles awayCommerce Center Boulevard data center (Bethlehem)
Bethlehem, Northampton County
🕒 Oct 20, 2026: Bethlehem City Council passed new data center rules 6-1. Because this plan was filed bef…
Reported in the news, not confirmed yet
What you can do
- Get told first.
We'll email you if anything changes in Emmaus Borough. - Go to borough meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
PPL Electric Utilities Corp. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.