TierPoint TekPark data center expansion (Breinigsville, Upper Macungie Township)
Also called: TekPark Data Center Expansion, TierPoint Allentown TekPark, 9999 Hamilton Boulevard
TierPoint already runs a data center at TekPark in Breinigsville. After buying the 137-acre campus in 2025, it began expanding its power to about 100 megawatts. PPL is building new power lines to serve it.
Where things stand: An existing data center (about 16 MW). TierPoint started a 100 MW power expansion that it expected to finish in late 2026.
๐ Latest update (Aug 2026): DEP asked for public comment on a stormwater permit for PPL's new Breinigsville-Tek Park 138/69 kV power line project to serve a data center project.
What we know
- ๐ Where9999 Hamilton Boulevard, Breinigsville (the 137-acre TekPark campus), Upper Macungie Township, Lehigh County
- ๐ข CompanyTierPoint
- ๐ค Built forTierPoint customers (colocation)
- ๐ณ Size137 acres
- โก Power it needs100 megawatts (about as much as 80,000 homes)
- ๐ Where the power comes fromPPL is building a new Breinigsville-Tek Park power line project to serve a data center project here.
- ๐ผ New power linesYes
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How many new buildings will the expansion add? ๐ I'll find out
- How much water will the expanded site use? ๐ I'll find out
- How many diesel generators are on site? ๐ I'll find out
- Who will use the new space? ๐ I'll find out
What happened so far
- Oct 2025TierPoint bought the TekPark campus and its data center (122,000 sq ft, about 16 MW) and began a 100 MW power expansion.
- Aug 2026DEP asked for public comment on a stormwater permit for PPL's new Breinigsville-Tek Park 138/69 kV power line project to serve a data center project.
Local votes and rules
๐ Data center rules
Upper Macungie Township proposed rules that would allow data centers as a conditional use in its General Industrial and Rural Technology zones. Buildings would need earth berms and must stay 200 feet from homes, schools, and churches. Neighboring Lower Macungie is using it as a model.
Drag the slider to compare the land before and now.
Where this comes from
- TierPoint acquires leased data center site in Pennsylvania, plans 100MW expansion ยท Data Center Dynamics ยท 2025
- In Case You Missed It: A.I./Data Center Articles - August 24 & 31 (lists DEP notice on PPL Breinigsville-Tek Park line) ยท PA Environment Digest ยท Aug 29, 2026