USA › Pennsylvania › Lackawanna County › Moscow Borough

No project in Moscow Borough, but 18 nearby

Who decides here: the Borough Council of Moscow Borough votes on zoning. The Lackawanna County Planning Commission usually reviews big projects too.

Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.

Nearby (within 15 miles)

Approved, not built yetabout 7 miles away

Project Gold (Clifton Township, Gouldsboro)

Clifton Township, Lackawanna County

1,000 acres

🕒 Aug 20, 2026: Judge ruled the township's old data center zoning law void; the settlement stays in effe…

Status unclearabout 8 miles away

Triboro data center site (Olyphant)

Olyphant, Lackawanna County

471 acres

🕒 Nov 4, 2026: Olyphant cancelled the Nov. 5 special meeting after the borough's lawyer said a neighbor…

Approved, not built yetabout 9 miles away

Sunnyside Road data center (Jessup)

Jessup, Lackawanna County

🕒 Sept 25, 2026: News reports said the Sunnyside Road project is 'tied up in litigation' after Council's …

Proposedabout 9 miles away

DBT-Data Lackawanna One (Jessup)

Jessup, Lackawanna County

39 acres

🕒 Sept 4, 2026: Application filed for a 200,000-square-foot, one-story data center.

Reported in the news, not confirmed yet

Proposedabout 9 miles away

Breaker Street data center campus (Jessup)

Jessup, Lackawanna County

131 acres

🕒 Sept 25, 2026: News reports said Breaker Street Associates LLC, tied to Catalyst Commercial Development…

Proposedabout 10 miles away

Dickson City Development data center (Bell Mountain)

Dickson City, Lackawanna County

🕒 Sept 18, 2026: The Times-Tribune listed the Bell Mountain project (4 buildings) as denied by the zoning…

Stopped or cancelledabout 11 miles away

Blakely data center campus

Blakely, Lackawanna County

209 acres

🕒 Sept 12, 2025: Developers withdrew the zoning change request after the borough declined another public …

Local votes and rules

📌 Other · Lackawanna County

Lackawanna County commissioners voted unanimously to hire EmPower Analytics Group for $165,000. Over 90 days the firm will study the pollution and health effects of more than a dozen proposed data center campuses and power plants in the county.

Sept 2026Source
Built & runningBeing builtApproved, not built yetProposedStopped or cancelledHollow dot (when zoomed in): exact site not known yet, pin shows the town

What you can do

  1. Get told first.
    We'll email you if anything changes in Moscow Borough.
  2. Go to borough meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
📣 Report something here

🔔 Get told first

We'll email you when something changes in Moscow Borough. Nothing else.

⚡ Your electric company

PPL Electric Utilities Corp. (company).

Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.