No project in Moscow Borough, but 18 nearby
Who decides here: the Borough Council of Moscow Borough votes on zoning. The Lackawanna County Planning Commission usually reviews big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Project Gold (Clifton Township, Gouldsboro)
Clifton Township, Lackawanna County
1,000 acres
🕒 Aug 20, 2026: Judge ruled the township's old data center zoning law void; the settlement stays in effe…
Status unclearabout 8 miles awayTriboro data center site (Olyphant)
Olyphant, Lackawanna County
471 acres
🕒 Nov 4, 2026: Olyphant cancelled the Nov. 5 special meeting after the borough's lawyer said a neighbor…
Approved, not built yetabout 9 miles awaySunnyside Road data center (Jessup)
Jessup, Lackawanna County
🕒 Sept 25, 2026: News reports said the Sunnyside Road project is 'tied up in litigation' after Council's …
Proposedabout 9 miles awayDBT-Data Lackawanna One (Jessup)
Jessup, Lackawanna County
39 acres
🕒 Sept 4, 2026: Application filed for a 200,000-square-foot, one-story data center.
Reported in the news, not confirmed yet
Proposedabout 9 miles awayBreaker Street data center campus (Jessup)
Jessup, Lackawanna County
131 acres
🕒 Sept 25, 2026: News reports said Breaker Street Associates LLC, tied to Catalyst Commercial Development…
Proposedabout 10 miles awayDickson City Development data center (Bell Mountain)
Dickson City, Lackawanna County
🕒 Sept 18, 2026: The Times-Tribune listed the Bell Mountain project (4 buildings) as denied by the zoning…
Stopped or cancelledabout 11 miles awayBlakely data center campus
Blakely, Lackawanna County
209 acres
🕒 Sept 12, 2025: Developers withdrew the zoning change request after the borough declined another public …
Local votes and rules
📌 Other · Lackawanna County
Lackawanna County commissioners voted unanimously to hire EmPower Analytics Group for $165,000. Over 90 days the firm will study the pollution and health effects of more than a dozen proposed data center campuses and power plants in the county.
What you can do
- Get told first.
We'll email you if anything changes in Moscow Borough. - Go to borough meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
PPL Electric Utilities Corp. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.