1 data center project in East Coventry Township
Who decides here: the Township Supervisors (in some larger townships, the Board of Commissioners) of East Coventry Township votes on zoning. The Chester County Planning Commission usually reviews big projects too.
In East Coventry Township
Nearby (within 15 miles)
Pennhurst data center (East Vincent Township)
East Vincent Township, Chester County
125 acres
π June 26, 2026: Penn Hurst Holdings DE LLC appealed the denial to the Chester County Court of Common Pleβ¦
Stopped or cancelledabout 4 miles away'Boutique' data center (North Coventry Township)
North Coventry Township, Chester County
17 acres
π Feb 23, 2026: Supervisors voted 3-2 to reject the sketch plan.
Reported in the news, not confirmed yet
Proposedabout 4 miles awayPublicker site data center (1301 Main St., Linfield, Limerick Township)
Limerick Township, Montgomery County
191.46 acres
π Sept 2026: Township agreed to the developer's request to delay hearings. The extension runs to Jan.β¦
Proposedabout 5 miles awayProject Laurel (MCD 7 LLC, Limerick Township)
Limerick Township, Montgomery County
192 acres Β· for Not named (developer cites NDAs)
π April 2026: Township planners asked for new will-serve letters from Pennsylvania American Water to sβ¦
Being builtabout 11 miles awaySentinel / Green Fig data center at Foote Mineral Superfund site (East Whiteland)
East Whiteland Township, Chester County
100 acres
π Aug 26, 2026: Second stop-work order until Aqua confirms enough water.
Proposedabout 14 miles awayUndisclosed data center (Hanover Land Development site, Upper Hanover Township)
Upper Hanover Township, Montgomery County
Reported in the news, not confirmed yet
East Coventry Township Board of Supervisors. We don't know yet if Constellation Energy data center (East Coventry Township, near Limerick nuclear plant) is on the agenda. Call the office to check before you go.
Local votes and rules
π Other Β· Chester County
The Chester County Planning Commission, working with Montgomery County, published a Data Center Ordinance Guide with sample zoning rules towns can copy. It suggests allowing large data centers only through a conditional use review, keeping them 1,000 feet from homes, and limiting height and noise.
What you can do
- Get told first.
We'll email you if anything changes in East Coventry Township. - Go to township meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
PECO Energy Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.
π Open tasks here
- What did the planning commission recommend, and has the board voted?
- How many buildings and megawatts?
- Would it take power directly from the nuclear plant?